Say what JBCC PBA clause 26.3 does to work identified as provisional.
Measure rock and fill from joint records the way the bill preamble says: in situ, compacted in place.
Value the adjustment as remeasured quantity less billed quantity, at the bill rate.
1 / 3
Why some quantities are provisional
Below ground the quantity surveyor cannot measure what nobody has seen. Rock in the trenches and unsuitable soil that must be replaced are billed as provisional: an honest estimate, priced at a firm rate, to be remeasured once the work is exposed. Under the JBCC Principal Building Agreement 6.2, clause 26.3, the value of work identified as provisional is omitted and the work as actually executed is added. The rate stays; the quantity changes.
ตัวอย่าง. A provisional item is not a promise of quantity. Neither side gains or loses from the estimate being wrong; the bill simply follows what was done.
2 / 3
Measure the way the bill was measured
The bill preamble fixes the measurement rules, and the remeasurement must use the same ones. South African bills follow the ASAQS standard system of measuring, and this bill states it plainly: excavation and rock in situ, net as dug, no allowance for bulking; fill compacted in place. Rock is length × trench width × depth of rock, never the full trench depth. Fill is plan area × compacted depth, never the loose volume on the delivery tickets, which includes the bulking that compaction removes.
ตัวอย่าง. 17.60 m³ delivered loose may compact to 13.50 m³ in place. Only the 13.50 is measured.
Length of rock run14.0 m
Trench width as dug0.7 m
Depth of rock0.4 m
Rock, m³ in situ3.92
3 / 3
The joint record is the evidence
Each measurement comes from a joint record signed by both sides while the work is open. Once the trench is backfilled nobody can check it again, so the record, not memory or an invoice, is what the quantity surveyor measures from. The adjustment for each item is (remeasured − billed quantity) × bill rate. A smaller quantity gives a negative adjustment, which reduces the contract value.
ตัวอย่าง. Billed 12.00 m³ at R 1,450.00, remeasured 5.32 m³: adjustment −6.68 × 1,450.00.
Remeasure two provisional items
A clinic's foundations are done. Rock and imported fill were billed provisionally. Measure them from the joint records and value the adjustment.
ไม่ได้วาดตามมาตราส่วน
โจทย์
Rock: run 1 is 14.0 m long with 0.4 m of rock; run 2 is 8.0 m long with 0.25 m. Trench width 0.7 m.
Fill: one area 9.0 m × 6.0 m, compacted depth 0.25 m. Delivery tickets: 17.6 m³ loose.
Bill: rock 12 m³ at R 1,450.00; fill 24 m³ at R 380.00, both provisional.
ขั้นตอนที่ 1 จาก 4
Rock in situ
Length × width × depth of rock, for both runs. How many m³ of rock?
คำใบ้: Use the rock depth, not the trench depth.
14.0 m × 0.7 m × 0.4 m + 8.0 m × 0.7 m × 0.25 m = 5.32 m³.
ขั้นตอนที่ 2 จาก 4
Fill compacted in place
Plan area × compacted depth. How many m³ of fill?
คำใบ้: The tickets measure loose material; ignore them.
9.0 m × 6.0 m × 0.25 m = 13.5 m³, against 17.6 m³ delivered loose.
ขั้นตอนที่ 3 จาก 4
Adjustment for rock
(Remeasured − billed) × rate. What is the adjustment for rock?
คำใบ้: The result is negative when less was found.
(5.32 − 12) × R 1,450.00 = −R 9,686.00.
1 Rock
2 Fill
3 Adjustment
1 Rock
2 Fill
3 Adjustment
ขั้นตอนที่ 4 จาก 4
Total adjustment
Add the adjustment for fill. What is the total adjustment to the contract value?