Course introduction · 3 min
AI-drafted progress claims, verified (France)
You are the cost manager for the steel frame contractor on a French public building job. Each month the contractor asks the client to pay for the work done: the payment application. Your firm's AI assistant has drafted May's one. In six tasks, in Contracts, you rebuild it from the site measurements, apply the price revision for inflation, the retention and the advance repayment, and check the invoice before it goes out.
Fictional project- Contract
- Public works contract with unit prices that follow an index, under CCAG-Travaux 2021
- Buyer
- A commune
- Starting point
- An AI draft of the May application, unchecked
- Work in the ERP
- 6 tasks, about 3 h 15 min
Who hands what to whom
Every arrow is a document that reaches your desk or leaves it, and the task where that happens.
Comes to you
- Site teamMeasures the work
- Measurement recordsTask 1
- AI billing assistantDrafted the application
- Draft amountsTask 2
- No revisionTask 3
- Retention on HTTask 4
- No repaymentTask 5
- Reverse chargeTask 6
YouCost manager (économiste), steel frame contractorGoes from you
- Payment applicationTask 3
- Invoice and amount dueTask 6
CommuneThe buyer, pays
The project and the people are fictional. Portraits are generated.
Your route through the job
First the work done, then each adjustment the contract makes to it, in the order they appear on the payment statement. Start with task 1: in Contracts you value April's work line by line from the measurements.
Work done
Task 1 · 15 min
The April situation: measured quantity × BPU price
- You produce
- April's work at initial prices
- Document
- Site measurement records (attachements)
- In the ERP
- Contracts
Work done
Task 2 · 30 min
Progress line by line: what the AI billed
- You produce
- May's work at initial prices, line by line
- Document
- Site measurement records (attachements)
- In the ERP
- Contracts
Adjustments
Task 3 · 35 min
The BT01 revision: the month the contract names
- You produce
- The price revision for May (prices moved with an index)
- Document
- Revision formula in the contract's special terms (CCAP) and the BT01 building cost index
- In the ERP
- Contracts
Adjustments
Task 4 · 35 min
Retention: 5 % of the revised payment with VAT
- You produce
- The retention
- Document
- Retention clause in the special terms (CCAP)
- In the ERP
- Contracts
Adjustments
Task 5 · 40 min
The advance: repaid once, from the right threshold
- You produce
- The advance repayment
- Document
- Advance clause in the special terms (CCAP)
- In the ERP
- Contracts
Invoice
Task 6 · 40 min
The invoice and the amount payable
- You produce
- The amount due
- Document
- Certified application and invoice
- In the ERP
- Contracts
From work done to the amount paid
Each step below is one task. The statement starts with the work at contract prices and ends with the cash that changes hands.
Blue is what the task adds; grey is carried over from before.
In short. Measure first. Then revise, add VAT, retain and repay in the order the contract sets, each on its own base.