Course introduction · 3 min

AI-drafted progress claims, verified (France)

You are the cost manager for the steel frame contractor on a French public building job. Each month the contractor asks the client to pay for the work done: the payment application. Your firm's AI assistant has drafted May's one. In six tasks, in Contracts, you rebuild it from the site measurements, apply the price revision for inflation, the retention and the advance repayment, and check the invoice before it goes out.

Start task 1

A sports hall under construction, steel frame and cladding.Fictional project
Vauclerc sports hallLot 04 steel frame, roofing, cladding · April to July 2026
Contract
Public works contract with unit prices that follow an index, under CCAG-Travaux 2021
Buyer
A commune
Starting point
An AI draft of the May application, unchecked
Work in the ERP
6 tasks, about 3 h 15 min

Who hands what to whom

Every arrow is a document that reaches your desk or leaves it, and the task where that happens.

Comes to you

  • Site teamMeasures the work
    • Measurement recordsTask 1
  • AI billing assistantDrafted the application
    • Draft amountsTask 2
    • No revisionTask 3
    • Retention on HTTask 4
    • No repaymentTask 5
    • Reverse chargeTask 6
YouCost manager (économiste), steel frame contractor

Goes from you

    • Payment applicationTask 3
    Project manager (maître d'œuvre)Checks and certifies
    • Invoice and amount dueTask 6
    CommuneThe buyer, pays

The project and the people are fictional. Portraits are generated.

Your route through the job

First the work done, then each adjustment the contract makes to it, in the order they appear on the payment statement. Start with task 1: in Contracts you value April's work line by line from the measurements.

  1. Work done

    Task 1 · 15 min

    The April situation: measured quantity × BPU price

    You produce
    April's work at initial prices
    Document
    Site measurement records (attachements)
    In the ERP
    Contracts
  2. Work done

    Task 2 · 30 min

    Progress line by line: what the AI billed

    You produce
    May's work at initial prices, line by line
    Document
    Site measurement records (attachements)
    In the ERP
    Contracts
  3. Adjustments

    Task 3 · 35 min

    The BT01 revision: the month the contract names

    You produce
    The price revision for May (prices moved with an index)
    Document
    Revision formula in the contract's special terms (CCAP) and the BT01 building cost index
    In the ERP
    Contracts
  4. Adjustments

    Task 4 · 35 min

    Retention: 5 % of the revised payment with VAT

    You produce
    The retention
    Document
    Retention clause in the special terms (CCAP)
    In the ERP
    Contracts
  5. Adjustments

    Task 5 · 40 min

    The advance: repaid once, from the right threshold

    You produce
    The advance repayment
    Document
    Advance clause in the special terms (CCAP)
    In the ERP
    Contracts
  6. Invoice

    Task 6 · 40 min

    The invoice and the amount payable

    You produce
    The amount due
    Document
    Certified application and invoice
    In the ERP
    Contracts

From work done to the amount paid

Each step below is one task. The statement starts with the work at contract prices and ends with the cash that changes hands.

Work at initial prices
Task 1WorkThe month's work at initial prices, from the measurements.
RevisionWork
Task 3ReviseThe BT01 index moves the price up or down with building costs.
RetentionVATWork and revision
Task 4Tax and retainVAT on top; retention, a small share, held back until the end.
Retention and advance repaidAmount due
Task 6PayLess the retention and the part of the advance paid back this month.

Blue is what the task adds; grey is carried over from before.

In short. Measure first. Then revise, add VAT, retain and repay in the order the contract sets, each on its own base.