Belosten School: handover, commissioning and warranties

A professional course of about 2 h with five tasks on the fictional case "Energy-efficiency measures, primary school, village of Belosten" in the completion phase: Form 15 findings report (акт обр.

  • Bulgaria · Български
  • 5 tasks
  • 3.5 h of study
  • Certificate of completion
Workspace: Belosten School: handover, commissioning and warranties
Log and price the defects

Who this course is for

Project manager — Invented character and company, drawn for this case
Your role in the caseProject manager
Балкантерм Строй ЕООД — Invented character and company, drawn for this case
The company in the caseБалкантерм Строй ЕООДMain contractor

Invented character and company, drawn for this case

What you will do

) with remarks in the punch list and a contractual retention, final Form 19 certificate (акт обр.) and final payment with full advance recovery, commissioning (category under the Spatial Planning Act (ЗУТ), certificate, construction file in Closeout), warranty periods under Ordinance No. 2 (Наредба) in the register, and a defect within the warranty period with release of the performance guarantee. You are the project manager at Balkanterm Stroy EOOD. All amounts come from the case register, and every typical mistake has a name.

Task steps: Belosten School: handover, commissioning and warranties
Follow the five task steps
Check result: Belosten School: handover, commissioning and warranties
Apply the double retention

You will be able to

Skills checked

  • Record a Bulgarian handover act (Form 15) with remarks as a punch list and value the withholding from contract unit rates
  • Prepare the final Form 19 certificate and invoice: executed works, unforeseen works, full advance recovery and VAT
  • Determine the construction category and the commissioning route under the Spatial Development Act and assemble the closeout file
  • Set statutory minimum warranty periods (Ordinance No 2/2003) in a defects-liability register
  • Handle a defect in the warranty period and the release of the performance guarantee under the Public Procurement Act

Tasks

Project manager — Invented character and company, drawn for this case
A day on this course
  1. 1Form 15 findings report (акт обр.): remarks, punch list and retained amountPunch list
  2. 2Final Form 19 certificate (акт обр.) No. 2 and final paymentContracts
  3. 3Commissioning: category, procedure and construction fileCloseout
  4. 4Warranty periods under Ordinance No. 2 (Наредба) in the registerDefects
  5. 5Defect within the warranty period and release of the performance guaranteeDefects

Certificate

Awarded when all 5 tasks pass the numbers, trace and explain checks.

3.5 h of study

Certificates →

Sample layout. Your certificate shows your name, the course version, the date and a verification ID.

Files you work with

Created in your OpenConstructionERP workspace the moment you enrol.

  • project
  • parties4 records
  • contract
  • Contractsprogress records5 lines
  • Variationschange register1 record

Before you start

No other course is needed first. You can start with this one.

Questions

How long does the course take?

5 tasks · 3.5 h of study

Is it free?

All 5 tasks free

Do I get a certificate?

Awarded when all 5 tasks pass the numbers, trace and explain checks.

Start free course All courses

Questions about this course? Write to info@datadrivenconstruction.io

Start free: task 1 of 5All 5 tasks free · 3.5 h of study

Start free course