Cheat sheet
Takeoff, progress payments and price adjustment (Turkey)
Every rule of the course on one page: how each figure is built, the mistake people usually make, and where it comes up at work. Print it or keep it open while you work.
- Rule
- Axis length, net height, large openings off. An opening under 1 m² counts as solid.
- How it is built
- A.05 outer wall net area = DD axis length × Net height: storey height − slab − Openings over 1 m² in the outer wall
- Total of the deducted openings = Outer wall: 14 windows P1 and entrance door K1 + Inner walls: 4 classroom doors K2
- A.06 inner wall net area = ID axis length × Net height − 4 classroom doors K2
- Usual mistake
- The wall stops under the slab: net height 3,40 − 0,40 = 3,00 m. The storey height counts the slab too.
- At work
- On every unit-price job the authority and the contractor measure the same sheet; a different takeoff means a dispute at the certificate.
- Rule
- 25 % on analysis prices, nothing for VAT. The approximate cost excludes VAT.
- How it is built
- A.07 internal plaster = Both faces of the inner walls: 2 × A.06 + Inner face of the outer wall: A.05
- Approximate cost, without VAT = Estimate total: quantity × analysis price + Profit and overheads: estimate × 25%
- Usual mistake
- That is the bare estimate. The analysis prices hold no profit or overheads: add 25 %.
- At work
- At the authority you build this before every tender; at the contractor you rebuild it to see where your bid stands.
- Rule
- Base index from the tender month, current index from the month of work. F = An × 0,90 × (Pn − 1).
- How it is built
- April Pn, three decimals = Each input: weight × April index ÷ February index + The same for all five inputs
- Certificate 1 price adjustment (F) = Work this period, An × B = 0.90 × Pn − 1
- Usual mistake
- The base index is the tender month's: February. March is the month of signature.
- At work
- With high inflation, price adjustment is its own line on every certificate, and the authority's control engineer checks each index.
- Rule
- A contractor's own delay earns it nothing. Late work takes the lower of the two indices.
- How it is built
- Certificate 2 price adjustment (F) = Work on programme × 0.90 × (May Pn − 1) + Late formwork × 0.90 × (chosen Pn − 1)
- Work on programme = Work this period − Late formwork
- Pn applied to the late formwork = The lower of April Pn and May Pn
- Usual mistake
- The May work is the result of the delay: the contractor does not gain from it, the lower Pn applies.
- At work
- Whenever work falls behind the programme, the certificate splits the period's work into on-programme and late.
- Rule
- Each deduction has its own base. Withholding and stamp duty on the amount, VAT withholding on VAT, extra guarantee on the adjustment.
- How it is built
- Amount payable to the contractor = This certificate's amount: work + price adjustment + VAT 20% − Total deductions
- Total deductions = Income tax 5% and stamp duty 9.48‰: on the amount + Withholding: 4/10 of the VAT + Extra guarantee: 6% of the price adjustment
- Usual mistake
- Income tax withholding is charged on the certificate amount without VAT.
- At work
- This is the last page of every certificate report; accounts raise the payment order from this figure.