Cheat sheet

Takeoff, progress payments and price adjustment (Turkey)

Every rule of the course on one page: how each figure is built, the mistake people usually make, and where it comes up at work. Print it or keep it open while you work.

Task 1

Wall takeoff from the plan: A-101

Theory (10 min)
Rule
Axis length, net height, large openings off. An opening under 1 m² counts as solid.
How it is built
  • A.05 outer wall net area = DD axis length × Net height: storey height − slab − Openings over 1 m² in the outer wall
  • Total of the deducted openings = Outer wall: 14 windows P1 and entrance door K1 + Inner walls: 4 classroom doors K2
  • A.06 inner wall net area = ID axis length × Net height − 4 classroom doors K2
Usual mistake
The wall stops under the slab: net height 3,40 − 0,40 = 3,00 m. The storey height counts the slab too.
At work
On every unit-price job the authority and the contractor measure the same sheet; a different takeoff means a dispute at the certificate.

Task 2

Estimate and approximate cost

Theory (10 min)
Rule
25 % on analysis prices, nothing for VAT. The approximate cost excludes VAT.
How it is built
  • A.07 internal plaster = Both faces of the inner walls: 2 × A.06 + Inner face of the outer wall: A.05
  • Approximate cost, without VAT = Estimate total: quantity × analysis price + Profit and overheads: estimate × 25%
Usual mistake
That is the bare estimate. The analysis prices hold no profit or overheads: add 25 %.
At work
At the authority you build this before every tender; at the contractor you rebuild it to see where your bid stands.

Task 3

Certificate 1 and April price adjustment

Theory (11 min)
Rule
Base index from the tender month, current index from the month of work. F = An × 0,90 × (Pn − 1).
How it is built
  • April Pn, three decimals = Each input: weight × April index ÷ February index + The same for all five inputs
  • Certificate 1 price adjustment (F) = Work this period, An × B = 0.90 × Pn − 1
Usual mistake
The base index is the tender month's: February. March is the month of signature.
At work
With high inflation, price adjustment is its own line on every certificate, and the authority's control engineer checks each index.

Task 4

Certificate 2: price adjustment on late work

Theory (10 min)
Rule
A contractor's own delay earns it nothing. Late work takes the lower of the two indices.
How it is built
  • Certificate 2 price adjustment (F) = Work on programme × 0.90 × (May Pn − 1) + Late formwork × 0.90 × (chosen Pn − 1)
  • Work on programme = Work this period − Late formwork
  • Pn applied to the late formwork = The lower of April Pn and May Pn
Usual mistake
The May work is the result of the delay: the contractor does not gain from it, the lower Pn applies.
At work
Whenever work falls behind the programme, the certificate splits the period's work into on-programme and late.

Task 5

Certificate 2: VAT, taxes and deductions

Theory (10 min)
Rule
Each deduction has its own base. Withholding and stamp duty on the amount, VAT withholding on VAT, extra guarantee on the adjustment.
How it is built
  • Amount payable to the contractor = This certificate's amount: work + price adjustment + VAT 20% − Total deductions
  • Total deductions = Income tax 5% and stamp duty 9.48‰: on the amount + Withholding: 4/10 of the VAT + Extra guarantee: 6% of the price adjustment
Usual mistake
Income tax withholding is charged on the certificate amount without VAT.
At work
This is the last page of every certificate report; accounts raise the payment order from this figure.