Cheat sheet

Home renovation: estimate, quote and variations (Australia)

Every rule of the course on one page: how each figure is built, the mistake people usually make, and where it comes up at work. Print it or keep it open while you work.

Task 1

Measure from the plan: tiles, board, skirting, cornice

Theory (9 min)
Rule
Net first, waste last, round up at the end. Waste goes on once.
How it is built
  • Wall tiling, net area = Bathroom perimeter × tiled height − Door − Window
  • Wall tiles to order = Net wall tiling × 1.10 for waste
  • Plasterboard sheets to order = Rear room walls less the three openings + Ceiling × 1.10 for waste ÷ One sheet, rounded up to whole sheets
Usual mistake
Take the door and window off first, then add the waste.
At work
On a small job you measure from the owners' plan yourself, and the supplier delivers exactly what you order.

Task 2

Build up the trade costs

Theory (9 min)
Rule
Cost is what you pay, without GST. Divide a GST-inclusive quote by 1.10.
How it is built
  • Plumber's quote excluding GST = Plumber's quote including GST ÷ 1.10
  • Direct cost, sections 1 to 3 = Own labour, section 1 + Subcontractors, section 2 + Materials, section 3
  • Subcontractors, section 2 = The four quotes, without GST + Tiler: laid area × rate
Usual mistake
GST is a tenth of the net, so the net is the total divided by 1.10, not 90 % of it.
At work
Every quote a small builder sends starts here: your own labour, the trades' quotes without GST, and materials with their waste.

Task 3

The quote: margin, PC items, provisional sums and GST

Theory (9 min)
Rule
Margin is on price, markup is on cost. Markup = margin ÷ (1 − margin). GST is the last row, once.
How it is built
  • Markup on cost = Margin on price, 20 % ÷ 1 − the margin
  • Quote price including GST = Direct cost, sections 1 to 3 + PC items + Provisional sums + Builder's margin + GST, 10 % of all of it
Usual mistake
20 % of cost is only a 16.7 % margin. Divide the margin by the share of the price that is cost.
At work
Every renovation quote carries PC items and provisional sums, and owners read them line by line before they sign.

Task 4

The payment schedule: deposit cap and stage payments

Theory (8 min)
Rule
The deposit limit runs on the price including GST. The last payment closes the schedule.
How it is built
  • Deposit including GST = Contract price including GST × 10 %, the legal maximum
  • Payment at practical completion = Contract price including GST − Deposit − The four stage payments
  • Claim 1: deposit excluding GST = Contract price excluding GST × 10 %
Usual mistake
The limit is 10 % of the price including GST, so the deposit may be higher.
At work
Every NSW home building contract carries a payment schedule like this one, and the owners pay against it stage by stage.

Task 5

Price a variation: the PC adjustment and a niche

Theory (8 min)
Rule
The PC item pays the difference; new work is at cost. Margin, then GST, then sign.
How it is built
  • Variation price including GST = Variation price excluding GST + GST, 10 %
  • Variation price excluding GST = PC adjustment: (new price − allowance) × order areas + Niche at cost + Your margin, as a markup on cost as in the quote
Usual mistake
The allowance was priced on the order area, with waste. Adjust on the same quantity.
At work
Owners change their minds on every renovation. Each change priced and signed in writing before the work keeps you paid.