Cheat sheet
Home renovation: estimate, quote and variations (Australia)
Every rule of the course on one page: how each figure is built, the mistake people usually make, and where it comes up at work. Print it or keep it open while you work.
- Rule
- Net first, waste last, round up at the end. Waste goes on once.
- How it is built
- Wall tiling, net area = Bathroom perimeter × tiled height − Door − Window
- Wall tiles to order = Net wall tiling × 1.10 for waste
- Plasterboard sheets to order = Rear room walls less the three openings + Ceiling × 1.10 for waste ÷ One sheet, rounded up to whole sheets
- Usual mistake
- Take the door and window off first, then add the waste.
- At work
- On a small job you measure from the owners' plan yourself, and the supplier delivers exactly what you order.
- Rule
- Cost is what you pay, without GST. Divide a GST-inclusive quote by 1.10.
- How it is built
- Plumber's quote excluding GST = Plumber's quote including GST ÷ 1.10
- Direct cost, sections 1 to 3 = Own labour, section 1 + Subcontractors, section 2 + Materials, section 3
- Subcontractors, section 2 = The four quotes, without GST + Tiler: laid area × rate
- Usual mistake
- GST is a tenth of the net, so the net is the total divided by 1.10, not 90 % of it.
- At work
- Every quote a small builder sends starts here: your own labour, the trades' quotes without GST, and materials with their waste.
- Rule
- Margin is on price, markup is on cost. Markup = margin ÷ (1 − margin). GST is the last row, once.
- How it is built
- Markup on cost = Margin on price, 20 % ÷ 1 − the margin
- Quote price including GST = Direct cost, sections 1 to 3 + PC items + Provisional sums + Builder's margin + GST, 10 % of all of it
- Usual mistake
- 20 % of cost is only a 16.7 % margin. Divide the margin by the share of the price that is cost.
- At work
- Every renovation quote carries PC items and provisional sums, and owners read them line by line before they sign.
- Rule
- The deposit limit runs on the price including GST. The last payment closes the schedule.
- How it is built
- Deposit including GST = Contract price including GST × 10 %, the legal maximum
- Payment at practical completion = Contract price including GST − Deposit − The four stage payments
- Claim 1: deposit excluding GST = Contract price excluding GST × 10 %
- Usual mistake
- The limit is 10 % of the price including GST, so the deposit may be higher.
- At work
- Every NSW home building contract carries a payment schedule like this one, and the owners pay against it stage by stage.
- Rule
- The PC item pays the difference; new work is at cost. Margin, then GST, then sign.
- How it is built
- Variation price including GST = Variation price excluding GST + GST, 10 %
- Variation price excluding GST = PC adjustment: (new price − allowance) × order areas + Niche at cost + Your margin, as a markup on cost as in the quote
- Usual mistake
- The allowance was priced on the order area, with waste. Adjust on the same quantity.
- At work
- Owners change their minds on every renovation. Each change priced and signed in writing before the work keeps you paid.