Cheat sheet

Earthworks: cut and fill, mass haul and pricing (Canada)

Every rule of the course on one page: how each figure is built, the mistake people usually make, and where it comes up at work. Print it or keep it open while you work.

Task 1

Cut and fill by average end area

Theory (9 min)
Rule
Each segment takes its own length. Cut and fill are measured apart, and the total is rounded once.
How it is built
  • Volume of one segment = Segment length × (area at the start + area at the end) ÷ 2
  • Cut for item 02.01 = Cut of segment 1 + cut of every other segment, rounded once
  • Fill for item 02.02 = Fill of segment 1 + fill of every other segment, rounded once
Usual mistake
That adds the two end areas and does not halve them. Average end area means the mean of the two.
At work
On every road job the estimator turns the engineer's cross-sections into volumes before pricing a single item.

Task 2

Swell, shrinkage and truck loads

Theory (9 min)
Rule
Compare cut and fill in one state. Borrow and waste are billed in bank m³; trucks count loose m³, rounded up.
How it is built
  • Compacted fill the usable cut gives = Usable cut, bank m³ × Shrinkage factor
  • Borrow to import, bank m³ = Fill still missing, compacted m³ ÷ Shrinkage factor
  • Truck loads = Waste, bank m³ × (1 + swell) ÷ Truck body, loose m³, rounded up
Usual mistake
That subtracts bank m³ of cut from compacted m³ of fill. The two are not the same volume, so convert first.
At work
Every earthworks bid balances cut against fill like this, and the haulage subcontract is booked from the truck count.

Task 3

Mass haul, free haul and overhaul

Theory (10 min)
Rule
Work each loop alone. A loop under the free haul earns no overhaul and never cancels another loop's.
How it is built
  • Overhaul of one loop = (Loop area − loop volume × free haul) ÷ Station, zero if negative
  • Overhaul for item 03.01 = Overhaul of loop 1 + Overhaul of loop 2
  • Surplus for item 03.02 = Last mass ordinate
Usual mistake
That nets the short loop against the long one. A loop under the free haul counts as zero, not as a credit.
At work
On road and site works the mass haul diagram decides where soil goes and which haul the owner pays as overhaul.

Task 4

Equipment productivity to a unit rate

Theory (10 min)
Rule
The slower part of the chain sets the output. Divide the cost of the whole spread by bank m³ per hour, then add the gate fee in bank m³.
How it is built
  • Production of the spread = Smaller of excavator and truck fleet output, loose ÷ (1 + swell)
  • Unit rate of 02.04 = Hourly cost of the whole spread ÷ Production of the spread + Gate fee per bank m³
  • Total of 02.04 = Unit rate in the bill × Quantity of 02.04
Usual mistake
The hourly cost is divided by the excavator's output. The trucks limit the spread, so divide by the slower figure.
At work
Estimators build rates like this for every earthworks item, from the fleet the foreman will actually send to site.

Task 5

Unsuitable material: a change to price

Theory (9 min)
Rule
Measure in bank m³, price per bank m³ and per tonne, leave HST off. The hole is backfilled to its own volume.
How it is built
  • Silt to remove, bank m³ = Each 20 m segment × the mean of its two end areas, added
  • Change value = Silt × (haul rate + gate fee for silt) + Granular B tonnes × rate per tonne
Usual mistake
That includes HST. The request is net, and the tax is added on the invoice.
At work
Unsuitable ground turns up on most earthworks jobs, and the change is priced from measured pits and agreed rates.