Cheat sheet
Earthworks: cut and fill, mass haul and pricing (Canada)
Every rule of the course on one page: how each figure is built, the mistake people usually make, and where it comes up at work. Print it or keep it open while you work.
- Rule
- Each segment takes its own length. Cut and fill are measured apart, and the total is rounded once.
- How it is built
- Volume of one segment = Segment length × (area at the start + area at the end) ÷ 2
- Cut for item 02.01 = Cut of segment 1 + cut of every other segment, rounded once
- Fill for item 02.02 = Fill of segment 1 + fill of every other segment, rounded once
- Usual mistake
- That adds the two end areas and does not halve them. Average end area means the mean of the two.
- At work
- On every road job the estimator turns the engineer's cross-sections into volumes before pricing a single item.
- Rule
- Compare cut and fill in one state. Borrow and waste are billed in bank m³; trucks count loose m³, rounded up.
- How it is built
- Compacted fill the usable cut gives = Usable cut, bank m³ × Shrinkage factor
- Borrow to import, bank m³ = Fill still missing, compacted m³ ÷ Shrinkage factor
- Truck loads = Waste, bank m³ × (1 + swell) ÷ Truck body, loose m³, rounded up
- Usual mistake
- That subtracts bank m³ of cut from compacted m³ of fill. The two are not the same volume, so convert first.
- At work
- Every earthworks bid balances cut against fill like this, and the haulage subcontract is booked from the truck count.
- Rule
- Work each loop alone. A loop under the free haul earns no overhaul and never cancels another loop's.
- How it is built
- Overhaul of one loop = (Loop area − loop volume × free haul) ÷ Station, zero if negative
- Overhaul for item 03.01 = Overhaul of loop 1 + Overhaul of loop 2
- Surplus for item 03.02 = Last mass ordinate
- Usual mistake
- That nets the short loop against the long one. A loop under the free haul counts as zero, not as a credit.
- At work
- On road and site works the mass haul diagram decides where soil goes and which haul the owner pays as overhaul.
- Rule
- The slower part of the chain sets the output. Divide the cost of the whole spread by bank m³ per hour, then add the gate fee in bank m³.
- How it is built
- Production of the spread = Smaller of excavator and truck fleet output, loose ÷ (1 + swell)
- Unit rate of 02.04 = Hourly cost of the whole spread ÷ Production of the spread + Gate fee per bank m³
- Total of 02.04 = Unit rate in the bill × Quantity of 02.04
- Usual mistake
- The hourly cost is divided by the excavator's output. The trucks limit the spread, so divide by the slower figure.
- At work
- Estimators build rates like this for every earthworks item, from the fleet the foreman will actually send to site.
- Rule
- Measure in bank m³, price per bank m³ and per tonne, leave HST off. The hole is backfilled to its own volume.
- How it is built
- Silt to remove, bank m³ = Each 20 m segment × the mean of its two end areas, added
- Change value = Silt × (haul rate + gate fee for silt) + Granular B tonnes × rate per tonne
- Usual mistake
- That includes HST. The request is net, and the tax is added on the invoice.
- At work
- Unsuitable ground turns up on most earthworks jobs, and the change is priced from measured pits and agreed rates.