OpenConstruction Academy
Sign in / Register
EN

Theory before task 4 · 10 min

Cost Plus Profit: valuing a delay from cost records

Cost Plus Profit for the late drawings

After this lecture you can

  1. Apply Sub-Clause 1.9: delayed drawings give extension of time and Cost Plus Profit.
  2. Build Cost from actual records: time-related overheads per day, idle labour, hired plant.
  3. Add the profit percentage of the Contract Data (5 % if none is stated).
1 / 3

Cost is what was actually spent

FIDIC 2017 defines Cost (Sub-Clause 1.1.19) as all expenditure reasonably incurred by the Contractor, on or off site, including overheads and similar charges, but not profit. Where a clause gives Cost Plus Profit, as 1.9 does for late drawings or instructions, the profit percentage of the Contract Data is added; if none is stated, it is 5 % (1.1.20). Cost is proved from records: payroll, hire invoices, site accounts. Tender rates are not Cost.

Example. Preliminaries per day in the tender are a price. Actual site overheads per day are a cost.
2 / 3

Three typical heads

Time-related site overheads: actual cost over a period ÷ its days, times the days of delay. Idle labour: workers standing × days until they could be demobilised × cost per worker-day. Plant and equipment on hire: daily hire × days of delay. Each head needs its record.

Example. Site overheads of 396,000 over 60 days are 6,600 per day.
Site overheads, actualSAR 396,000.00
Days in the period60
Per daySAR 6,600.00
3 / 3

Profit last, VAT outside

Add profit at the Contract Data percentage on the total Cost. The claim is stated before VAT, which is charged separately on the invoice.

Example. Cost 188,840 × 1.05 = 198,282.

Value a 23-day delay

Late drawings stopped a floor slab for 23 days. Value the claim from the records.

Not to scale
The problem
  • Actual time-related site overheads: SAR 396,000.00 over 60 days. Delay 23 days.
  • Crew of 10 standing 5 days before demobilisation, at SAR 290.00 per worker-day. Scaffold on hire SAR 980.00 per day.
  • Tender preliminaries: SAR 7,900.00 per day. Profit 5 % (Contract Data).
Step 1 of 3

Site overheads

Actual per day × days of delay. What is the overhead cost?

SAR 396,000.00 ÷ 60 × 23 = SAR 151,800.00.

SAR 151,800
  • Overheads SAR 151,800
  • Idle crew SAR 14,500
  • Scaffold SAR 22,540
SAR 151,800
  • Overheads SAR 151,800
  • Idle crew SAR 14,500
  • Scaffold SAR 22,540
Step 2 of 3

Cost

Add idle crew and scaffold hire. What is the total Cost?

SAR 151,800.00 + 10 × 5 × SAR 290.00 + SAR 980.00 × 23 = SAR 188,840.00.

Step 3 of 3

Cost Plus Profit

Add 5 %. What is claimed before VAT?

SAR 188,840.00 × 1.05 = SAR 198,282.00.

In short. Actual costs per head, from records; then the profit percentage. Tender rates do not measure Cost.

Check yourself

Question 1 of 3

Cost is SAR 200,000.00. The Contract Data states no profit percentage. What is Cost Plus Profit?

200,000.00 × 1.05 = SAR 210,000.00.
Question 2 of 3

Which figure measures site overheads in a Cost claim?

  • That is a price, which includes margin.

  • Right.

  • Cost is proved from the Contractor's records.

Question 3 of 3

Which clause gives Cost Plus Profit for late drawings?

  • Right: delayed drawings or instructions.

  • That sets the notice period.

  • 8.5 gives time; 1.9 gives the money.