Build the contract value from the original sum and the approved change orders, and keep unsigned ones out.
Compute earned revenue as contract value times the unrounded cost-to-cost ratio.
Read gross profit to date and estimated gross profit, and say what each tells the bank.
1 / 3
Contract value: what the owner has agreed to pay
The contract value on the WIP is the original stipulated sum plus every change order the owner has approved. Under ASC 606 a change to the contract counts once it is approved and creates enforceable rights. Many contractors' WIP rule, this company's included, waits for the owner's signature. Its cost may already sit in the estimate: then the margin on the WIP drops until the change order is signed. That is a reason to chase the signature, not to add the change order early.
Example. A CO-3 for $27,000, priced and sent but not signed, stays off the WIP until the owner signs it.
1 Original contract sum
2 CO-1, approved
3 CO-2, approved
4 Contract value on the WIP
2 / 3
Earned revenue: contract value times progress
Revenue on a construction contract follows the work as it is done: ASC 606 recognizes it over time by measuring progress. Earned revenue = contract value × cost to date / estimated cost at completion. Use the unrounded ratio; the two-decimal percent is for the report. Earned revenue is what the work done so far has earned. It is not what you have billed, and it is not what you have been paid.
Example. A job 45% complete on cost, with a $2,400,000 contract value, has earned $1,080,000.
Contract value$2,400,000
Cost to date$900,000
Estimate at completion$2,000,000
Percent complete45%
Earned revenue$1,080,000
3 / 3
Two gross profits
Gross profit to date = earned revenue − cost to date: what the books show so far. Estimated gross profit = contract value − estimated cost at completion: what the whole job will make. On a cost-to-cost job the first is the second times the percent complete, so the margin is the same share of revenue at every stage. A bank reading WIP schedules month after month watches the estimated gross profit. When it shrinks from one quarter to the next, the trade calls it profit fade.
Example. Cost in blue, gross profit in green. $180,000 to date is 45% of the $400,000 the job will make.
Earned revenue to date
$1,080,000 ($900,000 + $180,000)
Contract value
$2,400,000 ($2,000,000 + $400,000)
Earned revenue on a clinic job
Another job and another month. Build the contract value, then revenue and both gross profits.
Not to scale
The problem
Original contract sum $4,280,000.00.
CO-1 $96,500.00 and CO-2 $23,500.00, both approved. CO-3 $41,000.00, sent, not signed.
Cost to date $2,640,000.00; estimated cost at completion $3,960,000.00.
1 Original sum
2 CO-1
3 CO-2
4 Contract value
1 Original sum
2 CO-1
3 CO-2
4 Contract value
Step 1 of 4
Contract value
Add the approved change orders to the original sum. What is the contract value?
Hint: CO-3 is not signed.
$4,280,000.00 + $96,500.00 + $23,500.00 = $4,400,000.00. CO-3 stays out until the owner signs it.
Contract value$4,400,000.00
Cost to date / estimate66.6667%
Earned revenue?
Contract value$4,400,000.00
Cost to date / estimate66.6667%
Earned revenue$2,933,333.33
Step 2 of 4
Earned revenue
Contract value times cost to date over the estimate. What is the earned revenue, to the cent?
Hint: Multiply first, then divide, so the ratio stays unrounded.
$4,400,000.00 × $2,640,000.00 / $3,960,000.00 = $2,933,333.33. With the percent rounded to 66.67% you would get $2,933,480.00, off by $146.67.
$2,640,000.00?
Cost to date $2,640,000.00
Gross profit to date ?
$2,640,000.00
Cost to date $2,640,000.00
Gross profit to date $293,333.33
Step 3 of 4
Gross profit to date
Take cost to date off the earned revenue. What is the gross profit to date?
Hint: Revenue earned less cost spent.
$2,933,333.33 − $2,640,000.00 = $293,333.33.
Step 4 of 4
Estimated gross profit
Contract value less the estimate at completion. What will the whole job make?
Hint: No percent in this one.
$4,400,000.00 − $3,960,000.00 = $440,000.00. The job is two thirds complete on cost, and $293,333.33 is two thirds of $440,000.00.
In short. Contract value counts approved change orders only. Earned revenue uses the unrounded ratio. Gross profit to date is the estimated gross profit times the percent complete.
Check yourself
Question 1 of 3
CO-4 for an added loading canopy is priced and sent. The owner has not signed it, but its cost is already in the estimate. Under a WIP rule like this company's, what do you do at the close?
The cost is real, but the revenue is not agreed until the owner signs.
That keeps revenue to what the owner has agreed. The lower margin is the reason to chase the signature.
The cost is coming whether or not the owner signs. The estimate must show it.
It cannot go on the pay application before the owner signs it: it is not part of the contract sum yet.
Question 2 of 3
A job is 35% complete on cost. Its WIP line shows gross profit to date of $210,000 and estimated gross profit of $600,000. What does the bank read from this?
35% of $600,000 is $210,000: nothing is held back.
Gross profit to date is the estimated gross profit times the percent complete, as cost-to-cost intends.
Both gross profits are positive and consistent with each other.
Billing is a separate column. These two figures come from cost and contract value only.
Question 3 of 3
Contract value $1,650,000, cost to date $594,000, estimated cost at completion $1,320,000. What is the earned revenue?