Cheat sheet
Get paid under a CCDC 2 contract (Canada)
Every rule of the course on one page: how each figure is built, the mistake people usually make, and where it comes up at work. Print it or keep it open while you work.
- Rule
- A claim line is the month's movement: value to date less what earlier claims certified.
- How it is built
- Value to date of a trade = Contract value × Percent complete now
- Line for the period = Value to date − Certified in claims 1 to 4
- Claim 5 = Line GR + Line EE + the other five lines
- Usual mistake
- That is the value to date. Claims 1 to 4 already certified part of it: the claim is the movement.
- At work
- Every month the contractor's project accountant builds the claim from the schedule of values the consultant agreed.
- Rule
- Holdback comes off the claim; HST goes on what is invoiced now. The holdback's tax waits for its release.
- How it is built
- Holdback on claim 5 = Claim value without HST × Holdback rate
- Amount payable now = Due after holdback + HST on that amount
- Holdback held = Holdback on claims 1 to 4 + Holdback on claim 5
- Usual mistake
- The percentage has been applied to the HST-inclusive total. The base is the value of the work, excluding tax.
- At work
- Every Ontario contractor tracks holdback claim by claim, because it is paid only after substantial performance.
- Rule
- Own forces and sublet work carry different allowances. The sub's price already holds its own markup.
- How it is built
- Own-forces cost = Hours or quantity × rate, five lines
- Value of change order 7 = Own-forces cost × (1 + own allowance) + Subcontractor's price × (1 + sublet allowance)
- Usual mistake
- One allowance on everything: the subcontractor's price has been marked up at the own-forces rate.
- At work
- Site changes happen weekly; the contractor prices each one from time sheets, invoices and the contract's allowances.
- Rule
- The Act's periods override the contract's own term. A limit that ends on a holiday runs to the next day.
- How it is built
- Last day for the notice = Receipt + fourteen days, moved past holidays and the weekend
- Disputed amount as it would be paid = Envelope value × (1 − holdback rate) × (1 + HST rate)
- Usual mistake
- That is the plain fourteen days. Day fourteen is a holiday, so the limit moves on.
- At work
- Contractors diary these dates as soon as an invoice is served, so a late notice of non-payment is never missed.
- Rule
- Substantial performance is a sliding test on the adjusted price; the holdback is released with its tax.
- How it is built
- Threshold = 3 % of the first million + 2 % of the next million + 1 % of the rest
- Room left = Threshold − Cost to finish
- Holdback released = Line HR of release claim 6 × (1 + HST rate)
- Usual mistake
- That is ten per cent of the whole price: the work still to finish has not been taken out.
- At work
- Near handover the contractor tests substantial performance and asks the consultant for the certificate that releases holdback.