Cheat sheet

Get paid under a CCDC 2 contract (Canada)

Every rule of the course on one page: how each figure is built, the mistake people usually make, and where it comes up at work. Print it or keep it open while you work.

Task 1

Progress claim 5 from the schedule of values

Theory (9 min)
Rule
A claim line is the month's movement: value to date less what earlier claims certified.
How it is built
  • Value to date of a trade = Contract value × Percent complete now
  • Line for the period = Value to date − Certified in claims 1 to 4
  • Claim 5 = Line GR + Line EE + the other five lines
Usual mistake
That is the value to date. Claims 1 to 4 already certified part of it: the claim is the movement.
At work
Every month the contractor's project accountant builds the claim from the schedule of values the consultant agreed.

Task 2

Holdback, HST and what is actually payable

Theory (9 min)
Rule
Holdback comes off the claim; HST goes on what is invoiced now. The holdback's tax waits for its release.
How it is built
  • Holdback on claim 5 = Claim value without HST × Holdback rate
  • Amount payable now = Due after holdback + HST on that amount
  • Holdback held = Holdback on claims 1 to 4 + Holdback on claim 5
Usual mistake
The percentage has been applied to the HST-inclusive total. The base is the value of the work, excluding tax.
At work
Every Ontario contractor tracks holdback claim by claim, because it is paid only after substantial performance.

Task 3

Price a change order with markups

Theory (9 min)
Rule
Own forces and sublet work carry different allowances. The sub's price already holds its own markup.
How it is built
  • Own-forces cost = Hours or quantity × rate, five lines
  • Value of change order 7 = Own-forces cost × (1 + own allowance) + Subcontractor's price × (1 + sublet allowance)
Usual mistake
One allowance on everything: the subcontractor's price has been marked up at the own-forces rate.
At work
Site changes happen weekly; the contractor prices each one from time sheets, invoices and the contract's allowances.

Task 4

The prompt payment calendar

Theory (10 min)
Rule
The Act's periods override the contract's own term. A limit that ends on a holiday runs to the next day.
How it is built
  • Last day for the notice = Receipt + fourteen days, moved past holidays and the weekend
  • Disputed amount as it would be paid = Envelope value × (1 − holdback rate) × (1 + HST rate)
Usual mistake
That is the plain fourteen days. Day fourteen is a holiday, so the limit moves on.
At work
Contractors diary these dates as soon as an invoice is served, so a late notice of non-payment is never missed.

Task 5

Substantial performance and the holdback release

Theory (10 min)
Rule
Substantial performance is a sliding test on the adjusted price; the holdback is released with its tax.
How it is built
  • Threshold = 3 % of the first million + 2 % of the next million + 1 % of the rest
  • Room left = Threshold − Cost to finish
  • Holdback released = Line HR of release claim 6 × (1 + HST rate)
Usual mistake
That is ten per cent of the whole price: the work still to finish has not been taken out.
At work
Near handover the contractor tests substantial performance and asks the consultant for the certificate that releases holdback.