Cheat sheet

Payment certificates and variations (South Africa, JBCC)

Every rule of the course on one page: how each figure is built, the mistake people usually make, and where it comes up at work. Print it or keep it open while you work.

Task 1

Remeasure the provisional items

Theory (10 min)
Rule
Measure what was done, in situ. The provisional value goes out, the value as executed comes in.
How it is built
  • Rock, item 2.02 = Each trench: length × width × rock depth, added
  • Fill, item 2.04 = Each area × average depth, compacted in place, added
  • Adjustment = (Measured − provisional) × bill rate, item 2.02 + same for item 2.04
Usual mistake
Item 2.02 is extra over the excavation: measure only the rock, at its own depth in each trench.
At work
On every JBCC job the quantity surveyor remeasures provisional work from joint records signed on site.

Task 2

Price a contract instruction

Theory (10 min)
Rule
Bill rates first, cost plus 10 % last. Omitted work goes out at the bill rate.
How it is built
  • Value of CI 03 = One-brick walls at the 4.01 rate − Half-brick walls at the 4.02 rate + Gate: labour and materials × (1 + mark-up)
Usual mistake
The walls are at bill rates, which already carry profit. The 10 % goes on the gate only.
At work
The quantity surveyor values each contract instruction as it is issued, so the client always knows the running cost.

Task 3

The payment reduction and its release

Theory (9 min)
Rule
Option B holds 5 % until practical completion, then 2.5 %. The release is worked on the value at completion.
How it is built
  • Retention on the contract = Share held back under option B
  • Released at practical completion = Value at completion × (certified share after − certified share before)
Usual mistake
At practical completion the certified share goes from 95 % to 97.5 %. Half the reduction stays until the final certificate.
At work
Contractors plan cash flow around this release, and the principal agent certifies it at practical completion.

Task 4

Interim payment certificate 1

Theory (11 min)
Rule
Materials count only if on time, protected and insured. The 5 % comes off work and materials alike.
How it is built
  • Gross of claim 1 = Work from progress + CI 03 on line 7.01
  • Net certified = (Gross + qualifying materials) × certified share before completion
Usual mistake
Only the bricks qualify: the sheets are early (25.4.1), the frames off site without a guarantee (25.5), the cement unprotected (25.4.2).
At work
Every month the principal agent checks materials on site against these clauses before signing the certificate.

Task 5

Certificate 2: do not pay the bricks twice

Theory (10 min)
Rule
Built-in materials are work now. Value to date once, deduct what was certified, then tax what is left.
How it is built
  • Net to date = Value to date × certified share
  • Net certified = Net to date − Certificate 1
  • Amount due = Net certified × (1 + VAT rate)
Usual mistake
A certificate is cumulative: deduct the net amount certified in certificate 1.
At work
Principal agents check every draft certificate line by line; double-claimed materials are the classic catch.