Valdelagua civic centre: from the BC3 file to a new contract rate

Free course, about 2 hours, in five tasks on an invented case: a municipal civic centre (centro cívico) tendered by open procedure under Spain's Public Sector Contracts Act, Ley 9/2017 (LCSP).

  • Spain · Español
  • 5 tasks
  • 3.5 h of study
  • Certificate of completion
Workspace: Valdelagua civic centre: from the BC3 file to a new contract rate
Rebuild the four rate build-ups

Who this course is for

Bid estimator — Invented character and company, drawn for this case
Your role in the caseBid estimator
Construcciones Arlanzón — Invented character and company, drawn for this case
The company in the caseConstrucciones ArlanzónMain contractor

Invented character and company, drawn for this case

What you will do

You are a bid estimator and then site manager (jefe de obra) at Construcciones Arlanzón, a mid-sized contractor in Castilla y León. Rebuild the rate build-ups (precios descompuestos) of an incomplete BC3 file, close the tender base budget (presupuesto base de licitación) with 13% general expenses (GG) and 6% industrial profit (BI), bid with a percentage discount (baja), level roofing subcontract bids like-for-like, prepare the cumulative monthly payment certificate (certificación a origen) and fix a new contract rate (precio contradictorio). Every figure is recalculated against the case ledger, and every typical error is named. The documents and figures follow real Spanish practice.

Task steps: Valdelagua civic centre: from the BC3 file to a new contract rate
Build up four rates
Check result: Valdelagua civic centre: from the BC3 file to a new contract rate
Add indirect costs

You will be able to

Skills checked

  • Build Spanish unit rates (precios descompuestos) with ancillary means and indirect costs from a BC3/FIEBDC-3 file
  • Close the tender base budget: 13% GG and 6% BI on PEM, 21% VAT
  • Price a bid with a discount (baja) and compute the award coefficient and 5% performance guarantee
  • Level subcontract bids like-for-like (VAT-inclusive letters, excluded items) and apply the construction reverse charge
  • Prepare a cumulative monthly payment certificate (certificación a origen) under LCSP, without retention
  • Price a new contract rate (precio contradictorio) and test price-adjustment eligibility (LCSP art. 103)

Tasks

Bid estimator — Invented character and company, drawn for this case
A day on this course
  1. 1Rate build-ups and the works cost (PEM) of the civic centreBOQ
  2. 2From the PEM to the tender base budget and a bid with a discountBOQWatch 3 min
  3. 3Levelling roofing subcontract bids like-for-likeBid managementWatch 2 min
  4. 4Monthly payment certificate no. 2, cumulative (a origen)ContractsWatch 3 min
  5. 5New rate PC-01 (precio contradictorio) and contract modificationVariationsWatch 2 min

Certificate

Awarded when all 5 tasks pass the numbers, trace and explain checks.

3.5 h of study

Certificates →

Sample layout. Your certificate shows your name, the course version, the date and a verification ID.

Files you work with

Created in your OpenConstructionERP workspace the moment you enrol.

  • project
  • parties6 records
  • BOQbill of quantities15 lines
  • Bid managementbid package3 lines
  • contract
  • Contractsprogress records7 lines
  • Variationschange register1 record

Before you start

No other course is needed first. You can start with this one.

Questions

How long does the course take?

5 tasks · 3.5 h of study

Is it free?

All 5 tasks free

Do I get a certificate?

Awarded when all 5 tasks pass the numbers, trace and explain checks.

Start free course All courses

Questions about this course? Write to info@datadrivenconstruction.io

Start free: task 1 of 5All 5 tasks free · 3.5 h of study

Start free course