Two kinds of position outside the sum
A Bedarfsposition (Eventualposition) is work that may be needed, for example extra excavation if the ground turns out worse. It is priced now so that the price is fixed, but it is paid only if it is used. An Alternativposition offers a different way of doing the same work, for example another wall build-up. The client chooses one or the other, and until the client chooses, only the base option counts. The price must be there and must not be in the bill sum, because the bill sum is what the client will be asked to commit to.