The range test
Divide the direct cost by the gross floor area, a measure taken from the design (here DIN 277). Compare with the range the firm has seen on similar projects. If the figure is inside the range, no big section is missing and no decimal point has slipped. If it is outside, something large is wrong or the project is unusual: go and find out which. The test is blunt. Two errors that cancel each other pass it, and a ten per cent error in a sound-looking figure passes too.