Price revision: the formula, the month zero and the lag
The BT01 revision: the month the contract names
After this lecture you can
Read a revision formula with a fixed part and an index ratio.
Pick the month zero and the index month the contract names.
Round the coefficient the way the CCAG requires and apply it to the month's work.
1 / 4
Why prices are revised
On a contract that runs for months, steel and labour prices move. A revisable price follows an official index, here BT01, the all-trades building index published by INSEE. The contract's CCAP sets the formula; the CCAG sets how it is applied.
Example. Revision can go down as well as up. It follows the index, not the contractor's costs.
2 / 4
The formula has two parts
A typical formula is Cn = a + b × I(m − d) / I(0), with a + b = 1. The fixed part a is never revised; the case CCAP sets a = 0.15. I(0) is the index of month zero; I(m − d) the index a set number of months before the month the work was done, which allows for the time it takes the index to be published.
aFixed part, not revised
bRevised part, 1 − a
I(0)Index of month zero
I(m − d)Index d months before the work
3 / 4
Month zero is the tender, not the notification
CCAG-Travaux 2021 (article 9.4.4) takes the initial index value at the date the tender was submitted: the price was fixed then. Taking the notification month instead silently shifts the starting point, and usually lowers the revision.
Example. Tender in January, notification in March: month zero is January.
4 / 4
Round up, then apply to the month
The CCAG requires the coefficient to be rounded up to the next thousandth before it is applied (article 10.5). It applies to the work of the month only; the revision is that work times (Cn − 1). Applying it to the cumulative total revises earlier months twice.
Coefficient calculated1.0164
Rounded up to the thousandth1.017
Revise one month
Another contract, same kind of formula: Cn = 0.15 + 0.85 × I(m − 2) / I(0). Type your answer first.
Not to scale
The problem
Tender in October (month zero), index 120.4.
Work done in March: €96,000 at initial prices. The index of January, two months earlier, is 123.9.
Unrounded Cn1.0247
Rounded up1.025
Rise?
Unrounded Cn1.0247
Rounded up1.025
Rise2.5%
Step 1 of 2
Price rise
Cn = 0.15 + 0.85 × 123.9 / 120.4, rounded up to the thousandth. By what percentage does the price rise, Cn − 1?
Hint: Work out Cn to four decimals, round it up to three, then take away 1.
0.85 × 123.9 / 120.4 = 0.8747, plus 0.15 is 1.0247, rounded up to 1.025: a rise of 2.5%.
Work
€96,000
Revised
?
Work
€96,000
Revised
€98,400 (€96,000 + €2,400)
Step 2 of 2
Revision
What is the revision for March?
Hint: The month's work times the rise.
€96,000 × 2.5% = €2,400.00.
In short. Month zero is the tender month, the index month is the one the formula names, the coefficient is rounded up, and it applies to the month's work only.
Check yourself
Question 1 of 3
Tender in February, notification in April, work starts in May. Which is month zero?
The initial index value is that of the tender date.
The notification fixes the start of the contract, not the price.
Work starting does not reset the price.
Question 2 of 3
A coefficient comes out at 1.0312. What do you apply?
That is rounded to the nearest. The CCAG rounds up.
Rounded up to the next thousandth.
The coefficient is rounded before it is applied.
Question 3 of 3
Work of the month €64,000; Cn = 1.018. What is the revision?