What retention is for
The retention (retenue de garantie) holds back part of each payment until the end of the guarantee of completion, to cover reservations at handover. The Public Procurement Code caps it at 5 % of the contract amount; the contract's CCAP sets the actual rate and its base. A bank guarantee can replace it.