The advance and its repayment

The advance: repaid once, from the right threshold

After this lecture you can

  1. Say when a public buyer must pay an advance.
  2. Compute a linear repayment between two thresholds.
  3. Take only this statement's share of the repayment.
1 / 4

Why an advance

The Public Procurement Code (article R2191-3) makes an advance compulsory when the initial amount exceeds €50,000 before tax and the period of performance exceeds two months, unless the contractor declines it. It helps the contractor buy materials before the first payment. It is then repaid out of the payments that follow.

Example. On this case the advance is 30 % of the initial amount with VAT, paid in the first month.
2 / 4

Repaid between two thresholds

The case CCAP repays the advance in a straight line, starting when the work executed at initial prices reaches 65 % of the initial amount and finishing at 80 %. Below 65 % nothing is repaid; above 80 % everything is. In between, the share repaid is the share of that 15-point band already crossed.

Executed, %
75 (65 + 10)
Repayment band, %
80 (65 + 15)
3 / 4

Cumulative, then the month

Work out how much should have been repaid by the end of this month, from the cumulative work executed, and deduct what earlier statements already repaid. A draft that waits for 80 % repays nothing for months and then everything at once; a draft that starts from zero rather than 65 % repays too early.

Executed share xCumulative work at initial prices ÷ initial amount
Repaid by nowAdvance × (x − 65 %) ÷ 15 %
This statementRepaid by now − repaid before
4 / 4

Read the cumulative from the ERP

The executed share uses the verified cumulative, at initial prices, without revision or VAT. Use the figure from the statement you rebuilt, not the draft's.

Example. A wrong cumulative moves the repayment by the whole band's slope: here, 1/15 of the advance per point.

Repay part of an advance

Another contract. Type your answer first.

Not to scale
The problem
  • Initial amount before VAT €600,000. Advance €108,000, paid in the first month.
  • Cumulative work at initial prices: €450,000 at the end of this month; below 65 % at the end of last month, so nothing repaid yet.
Executed
?
Executed
75 (65 + 10)
Step 1 of 2

Executed share

What share of the initial amount has been executed, in per cent?

€450,000 ÷ €600,000 = 75%.

Advance€108,000.00
Band crossed66.6667%
Repaid?
Advance€108,000.00
Band crossed66.6667%
Repaid€72,000.00
Step 2 of 2

Repayment

How much of the advance does this statement repay?

€108,000 × (75% − 65) ÷ 15 = €72,000.00.

In short. Start at 65 %, finish at 80 %, in a straight line, on the verified cumulative; deduct what was repaid before.

Check yourself

Question 1 of 2

Work executed has reached 60 % of the initial amount. How much of the advance is repaid?

  • Repayment starts at 65 %.

  • The repayment follows the band, not the executed share.

  • That happens at 80 %.

Question 2 of 2

Advance €90,000. Executed share 71 %, nothing repaid before. What does this statement repay?

€90,000 × 6 ÷ 15 = €36,000.