Theory before task 6 · 8 min

The invoice and the amount due

The invoice and the amount payable

After this lecture you can

  1. Tell when the VAT reverse charge applies in construction, and when it does not.
  2. Build the amount due in the order of the payment statement.
  3. Deduct the advance repayment once, after VAT.
1 / 4

Reverse charge is for subcontractors

The French tax code (article 283, 2 nonies) makes the customer pay the VAT on construction work done by a subcontractor for a taxable main contractor. A main contractor invoicing a public buyer is not in that position: it charges VAT at the normal rate of 20 % (article 278), and the buyer pays it.

Subcontractor to main contractorReverse charge
Main contractor to a communeVAT at 20 % on the invoice
2 / 4

The order of the statement

CCAG-Travaux 2021 (article 12.2.1) sets out the payment statement: work at initial prices, VAT, revision, the advance to be repaid, the retention. In money terms: work plus revision, VAT on both, then the retention and the advance repayment come off the amount with VAT.

Work€84,000
Revision€1,300
VAT 20 %€17,060
Total with VAT€102,360
3 / 4

The advance comes off once

The case CCAP deducts the advance repayment from the amount with VAT, with no VAT of its own: the advance was already taxed when it was paid. Deducting it before VAT, or adding VAT to it, counts the tax twice in one direction or the other.

Example. Retention and advance repayment are both deductions from the same line: the total with VAT.
4 / 4

The invoice and the statement must agree

The invoice the ERP produces carries the work before VAT and the VAT. The certified statement carries the adjustments. The amount due is one figure that both explain: if they disagree, one of them is wrong.

Example. A draft that drops the VAT pays the contractor a sixth less than it is owed, and the buyer pays it later or not at all.

From the statement to the amount due

The month from the earlier examples. Type your answer first.

Not to scale
The problem
  • Work €96,000, revision €2,400, VAT 20 %.
  • Retention 5 % on the amount with VAT. Advance repayment €72,000.
€96,000€19,680
  • Work €96,000
  • Revision €2,400
  • VAT €19,680
€96,000€19,680
  • Work €96,000
  • Revision €2,400
  • VAT €19,680
Step 1 of 2

Total with VAT

What is the total with VAT?

(€96,000 + €2,400) × 1.2 = €118,080.00.

€118,0801−€5,9042−€72,0003?4
  • 1 With VAT
  • 2 Retention
  • 3 Advance repaid
  • 4 Due
€118,0801−€5,9042−€72,0003€40,1764
  • 1 With VAT
  • 2 Retention
  • 3 Advance repaid
  • 4 Due
Step 2 of 2

Amount due

What is the amount due?

€118,080.00 − 5 % retention − €72,000 = €40,176.00.

In short. Invoice with VAT, then deduct retention and the advance repayment from the amount with VAT, each once.

Check yourself

Question 1 of 2

A main contractor invoices a commune for building work. Who pays the VAT?

  • VAT at 20 % is charged as normal.

  • Reverse charge applies to a subcontractor working for a taxable main contractor.

Question 2 of 2

Total with VAT €60,000; retention 5 %; advance repayment €12,000. What is due?

€60,000 − €3,000 − €12,000 = €45,000.