Course introduction · 3 min

Final account (UK, NEC4 Option B)

You are the builder's commercial manager on a two-storey health centre. The building is finished and the defects year has run out. What is left is money: which changes were agreed, which are still argued, what the remeasured bill is worth, and the last payment of the job. In five tasks you close the final account with the client's Project Manager.

Start task 1

The finished health centre after handover.Fictional project
Ashbrook Community Health CentreTwo-storey health centre · Defects Certificate November 2028
Building
Two-storey community health centre, built in 2027
Contract
NEC4 ECC Option B, a UK contract priced with a bill of quantities, with retention (X16)
Account
Seven compensation events, three remeasured bill items, one uncorrected Defect
Work in the ERP
5 tasks, about 1 h 37 min

Who hands what to whom

Every arrow is a record that reaches your desk or leaves it, and the task where that happens.

Comes to you

  • Project ManagerAssesses for the Client
    • Acceptance of CE-04Task 1
    • Own assessment of CE-05Task 2
  • Site teamMeasured the as-built
    • As-built quantitiesTask 4
YouCommercial manager, main contractor

Goes from you

    • Outturn figureTask 1
    • Final accountTask 5
    ClientHealth partnership
    • Failure to reply noticeTask 3
    • Remeasured billTask 4
    Project ManagerAssesses for the Client

The project and the people are fictional. Portraits are generated.

Your route through the job

Three tasks settle the compensation events, one the bill, one the last payment. Start with task 1: in Variations you read what the register says is agreed.

  1. Compensation events

    Task 1 · 12 min

    What is agreed: the CE register at Completion

    You produce
    The Prices with every implemented event
    Document
    CE register and the Project Manager's letter
    In the ERP
    Variations
  2. Compensation events

    Task 2 · 20 min

    The Project Manager's own assessment of CE-05

    You produce
    CE-05 at the Project Manager's value, and the balance in dispute
    Document
    Quotation and the clause 64 assessment
    In the ERP
    Variations
  3. Compensation events

    Task 3 · 18 min

    CE-08: a quotation nobody answered

    You produce
    CE-08 accepted by silence, and the date it happened
    Document
    Quotation and the failure notice
    In the ERP
    Variations
  4. Bill and payment

    Task 4 · 22 min

    Remeasurement under Option B

    You produce
    The remeasured bill and the change it makes
    Document
    As-built measurement
    In the ERP
    BOQ
  5. Bill and payment

    Task 5 · 25 min

    The final assessment

    You produce
    The amount due in the final assessment
    Document
    Final account
    In the ERP
    Variations

From the register to the last payment

Each step below is one task. The account is final when every event is decided, the bill shows what was built, and the last payment has been worked out.

Still openImplemented
Task 1AgreedOnly implemented events count. Quotations wait; late claims are out.
In disputeImplemented
Task 2AssessedWhere the Project Manager disagrees, its own assessment is what gets paid.
EventsBill
Task 4RemeasuredOption B pays the quantities built, once, at the bill rates.
Last paymentFinal Prices
Task 5SettledThe last assessment releases the retention and charges any Defect left unfixed.

Blue is what the task adds; grey is carried over from before.

In short. Count what was agreed, record what was assessed, pay each quantity once, and settle within four weeks of the Defects Certificate.