Course introduction · 3 min
Final account (UK, NEC4 Option B)
You are the builder's commercial manager on a two-storey health centre. The building is finished and the defects year has run out. What is left is money: which changes were agreed, which are still argued, what the remeasured bill is worth, and the last payment of the job. In five tasks you close the final account with the client's Project Manager.
Fictional project- Building
- Two-storey community health centre, built in 2027
- Contract
- NEC4 ECC Option B, a UK contract priced with a bill of quantities, with retention (X16)
- Account
- Seven compensation events, three remeasured bill items, one uncorrected Defect
- Work in the ERP
- 5 tasks, about 1 h 37 min
Who hands what to whom
Every arrow is a record that reaches your desk or leaves it, and the task where that happens.
Comes to you
Project ManagerAssesses for the Client- Acceptance of CE-04Task 1
- Own assessment of CE-05Task 2
Site teamMeasured the as-built- As-built quantitiesTask 4
YouCommercial manager, main contractorGoes from you
- Outturn figureTask 1
- Final accountTask 5
ClientHealth partnership- Failure to reply noticeTask 3
- Remeasured billTask 4
Project ManagerAssesses for the Client
The project and the people are fictional. Portraits are generated.
Your route through the job
Three tasks settle the compensation events, one the bill, one the last payment. Start with task 1: in Variations you read what the register says is agreed.
Compensation events
Task 1 · 12 min
What is agreed: the CE register at Completion
- You produce
- The Prices with every implemented event
- Document
- CE register and the Project Manager's letter
- In the ERP
- Variations
Compensation events
Task 2 · 20 min
The Project Manager's own assessment of CE-05
- You produce
- CE-05 at the Project Manager's value, and the balance in dispute
- Document
- Quotation and the clause 64 assessment
- In the ERP
- Variations
Compensation events
Task 3 · 18 min
CE-08: a quotation nobody answered
- You produce
- CE-08 accepted by silence, and the date it happened
- Document
- Quotation and the failure notice
- In the ERP
- Variations
Bill and payment
Task 4 · 22 min
Remeasurement under Option B
- You produce
- The remeasured bill and the change it makes
- Document
- As-built measurement
- In the ERP
- BOQ
Bill and payment
Task 5 · 25 min
The final assessment
- You produce
- The amount due in the final assessment
- Document
- Final account
- In the ERP
- Variations
From the register to the last payment
Each step below is one task. The account is final when every event is decided, the bill shows what was built, and the last payment has been worked out.
Blue is what the task adds; grey is carried over from before.
In short. Count what was agreed, record what was assessed, pay each quantity once, and settle within four weeks of the Defects Certificate.