Theory before task 1 · 7 min

What is agreed: the register at Completion

What is agreed: the CE register at Completion

Course introduction

After this lecture you can

  1. Tell an implemented compensation event from a quotation and a barred claim.
  2. Read the agreed value, not the estimate, on each request.
  3. State the Prices with every implemented event.
1 / 3

Four states of a compensation event

An event is notified, then quoted, then either accepted or assessed by the Project Manager. Only then is it implemented, and only an implemented event changes the Prices (clause 65.1). A quotation is an offer; until it is decided it is a number the Contractor would like, not one the Client owes.

Example. On this job the register holds approved, rejected and submitted events side by side. Only the approved ones belong in the Prices.
2 / 3

The eight-week bar

If the Contractor does not notify an event within eight weeks of becoming aware of it, the Prices and the Completion Date do not change for it (61.3), unless the event is one the Project Manager should have notified. A barred claim stays on the register as a record, rejected, worth nothing.

Example. CE-03 was notified nine weeks after the site team knew. It adds nothing, however fair the claim.
Limit, weeks
8
CE-03, weeks to notice
9 (8 + 1)
Common mistake

Adding the quotations

A cost report that adds every figure on the register looks complete and is wrong in the Contractor's favour. The Client's board then signs off a number nobody has agreed, and the gap surfaces at the final account as a loss.

£5,0001+£7,8002£12,8003
  • 1 Implemented events
  • 2 Quotations added by mistake
  • 3 Reported, overstated

The Prices in April 2027, on the same job

The job before CE-03 was decided. Two events implemented, one claim pending.

Not to scale
The problem
  • Prices at the Contract Date £1,169,739.13.
  • CE-01 implemented at £781.95. CE-02 quoted at £2,060.53, implemented at the Project Manager's value £1,829.53.
  • CE-03 claimed at £3,140, notified nine weeks after awareness.
Step 1 of 2

Which events count

How many of the three events change the Prices?

CE-01 and CE-02 are implemented; CE-03 is barred. 2 events count.

Prices at the Contract Date£1,169,739.13
CE-01£781.95
CE-02 agreed£1,829.53
Prices now?
Prices at the Contract Date£1,169,739.13
CE-01£781.95
CE-02 agreed£1,829.53
Prices now£1,172,350.61
Step 2 of 2

The Prices

What are the Prices after the implemented events?

£1,169,739.13 + £781.95 + £1,829.53 = £1,172,350.61.

In short. The Prices move by agreed values only. A quotation waits; a barred claim never counts.

Check yourself

Question 1 of 2

A quotation of £4,000 has been with the Project Manager for one week. Is it in the Prices?

  • Right. It counts once it is implemented.

  • A quotation is an offer until it is decided.

  • There is no partial counting of quotations.

Question 2 of 2

Prices at the Contract Date £800,000. Implemented events £6,000 and £2,500. One quotation of £3,000 is pending. What are the Prices now?

£800,000 + £6,000 + £2,500 = £808,500.