When and what
The Project Manager makes the final assessment no later than four weeks after the Defects Certificate (53.1). It is the last assessment of the contract: the final Prices, less what has been paid, with the rest of the retention released (X16) and any amount the Contractor must pay, such as the cost of an uncorrected Defect (46.1).