Theory before task 5 · 9 min

The final assessment

The final assessment

After this lecture you can

  1. Know when the final assessment is made (53.1) and what makes it conclusive.
  2. Build the final total from the Prices, the events and the remeasurement.
  3. Work out the amount due: release the retention, charge the uncorrected Defect.
1 / 4

When and what

The Project Manager makes the final assessment no later than four weeks after the Defects Certificate (53.1). It is the last assessment of the contract: the final Prices, less what has been paid, with the rest of the retention released (X16) and any amount the Contractor must pay, such as the cost of an uncorrected Defect (46.1).

Example. Disputed parts go in at the Project Manager's values. The Contractor's remedy is adjudication, not a lower figure in the account.
2 / 4

The shape of the last payment

Everything agreed, less everything paid. What was paid already had the retention held back, so releasing it is part of the amount due, not a separate step.

£1,000,0001−£985,0002−£5003£14,5004
  • 1 Final Prices
  • 2 Paid to date
  • 3 Uncorrected Defect
  • 4 Amount due
Common mistake

Holding the retention twice

Paid to date is already net of the retention still held. Taking retention off the final total again keeps back money the contract now releases, and the Contractor's last payment comes out short by the whole retention.

Example. Check: after the final assessment nothing is retained. If your workings still show a retention line, it is counted twice.
4 / 4

If the Contractor disagrees

The assessment becomes conclusive unless it is referred to the Adjudicator, and then the tribunal, within the periods the contract sets. Under the Construction Act a party may refer a dispute to adjudication at any time, and the contract's dispute option (W2 in England) follows that.

Example. A disputed balance is pursued by referral, not by holding the account open.

Paid to date at Completion, on the same job

The last assessment before the Defects Certificate, from the handover course.

Not to scale
The problem
  • Price for Work Done to Date £1,172,350.61.
  • Retention 3 %, half released at Completion.
  • Every certified amount has been paid.
Step 1 of 2

Retention held

How much retention is still held?

£1,172,350.61 × 3 % ÷ 2 = £17,585.26.

PWDD£1,172,350.61
Retention still held−£17,585.26
Paid to date?
PWDD£1,172,350.61
Retention still held−£17,585.26
Paid to date£1,154,765.35
Step 2 of 2

Paid to date

How much has the Contractor been paid?

£1,172,350.61 − £17,585.26 = £1,154,765.35. This is what the final assessment deducts.

In short. Paid to date is net of the retention still held, so the final assessment deducts it once and releases the rest.

Check yourself

Question 1 of 2

The Defects Certificate was issued on 1 March. By when must the final assessment be made?

  • Right (53.1).

  • Eight weeks is the notification bar for compensation events.

  • 53.1 sets its own limit.

Question 2 of 2

Final Prices £900,000. Paid to date £882,000, net of retention still held. An uncorrected Defect is assessed at £1,200. What is due?

£900,000 − £882,000 − £1,200 = £16,800.

Read the source

Free official texts. The lecture cites clause numbers and puts the rules in its own words.