Theory before task 4 · 8 min

Remeasurement under Option B

Remeasurement under Option B

After this lecture you can

  1. Know what Option B pays: the quantities built, at bill rates.
  2. Apply the two tests of clause 60.4 to a quantity change.
  3. Remeasure around a compensation event, not through it.
1 / 3

The bill follows the work

Under Option B the Contractor is paid the quantities actually completed at the rates in the bill. A difference between the bill quantity and the final quantity simply changes what is paid. A mistake in the bill itself is corrected as a compensation event (60.6).

Example. Two more square metres of wall are paid at the wall's bill rate. Nothing more needs to be agreed.
2 / 3

When a quantity change is a compensation event

Clause 60.4 makes it one only if both tests are met: the change in rate times quantity is more than half a percent of the total of the Prices at the Contract Date, and the difference changes the Defined Cost per unit. Otherwise the bill rate stands.

Prices at the Contract Date£1,169,739.13
0.5 % threshold£5,848.70
Common mistake

Remeasuring through a compensation event

When a compensation event changed what is built, the as-built measure already includes the change. Put that measure straight into the bill and the same work is paid twice: once by the event, once by the bill. Take the event's quantities back out first.

£4,0001+£9602£4,9603
  • 1 Bill item, remeasured
  • 2 Paid again by mistake
  • 3 Overpaid total

Skirting, on the same job

SK1 and SK2 were remeasured too. CE-01 changed the skirting in F01-F03 from SK2 to SK1.

Not to scale
The problem
  • Bill: SK1 193.52 m at £9.80; SK2 103.9 m at £12.60.
  • As-built: SK1 259.1 m, SK2 38.6 m.
  • CE-01 paid the swap of 65.1 m of skirting in F01-F03.
Step 1 of 3

Final SK1

What is the final SK1 quantity for the bill, in m?

259.1 − 65.1 = 194 m.

Step 2 of 3

Final SK2

What is the final SK2 quantity for the bill, in m?

38.6 + 65.1 = 103.7 m.

SK1 change£4.70
SK2 change−£2.52
Net?
SK1 change£4.70
SK2 change−£2.52
Net£2.18
Step 3 of 3

Adjustment

What is the net change from remeasuring the skirting?

SK1 adds a little, SK2 takes a little back: £2.18 in all.

In short. Remeasure each item around the events that changed it, price the differences at bill rates, and test any large change against 60.4.

Check yourself

Question 1 of 2

A bill item grows by £2,000 at its bill rate on £1,000,000 of Prices, and its cost per unit is unchanged. Is it a compensation event?

  • Right. £2,000 is below £5,000 and the unit cost has not changed.

  • Only changes that meet both tests of 60.4.

Question 2 of 2

A floor item: bill 200 m² at £32. As-built 260 m², of which 50 m² were paid by a compensation event. What does remeasurement add?

(260 − 50 − 200) × £32 = £320.