Two clocks, not one
The Project Manager replies to a quotation within two weeks (62.3). If it does not, the Contractor may notify that failure. If the failure continues for two more weeks after that notice, the quotation is treated as accepted (62.6). The second clock starts at the Contractor's notice, not at the end of the first.