OpenConstruction Academy
Sign in / Register
EN

Theory before task 3 · 6 min

A quotation nobody answered

CE-08: a quotation nobody answered

After this lecture you can

  1. Know the Project Manager's reply period for a quotation (62.3).
  2. Know when silence becomes acceptance (62.6).
  3. Count the days from a quotation to its deemed acceptance.
1 / 2

Two clocks, not one

The Project Manager replies to a quotation within two weeks (62.3). If it does not, the Contractor may notify that failure. If the failure continues for two more weeks after that notice, the quotation is treated as accepted (62.6). The second clock starts at the Contractor's notice, not at the end of the first.

Reply period, days
14
Gap before the notice
17 (14 + 3)
Two weeks after the notice
31 (14 + 3 + 14)
Common mistake

Treating silence as acceptance

Recording a quotation as accepted the day the reply period ends gives the Project Manager a strong objection, and the notice that would have started the real clock was never sent. Send the notice the day after the reply date passes.

Example. A diary entry for each reply date is the whole control.

If CE-04 had gone unanswered, on the same job

A what-if. In fact the Project Manager accepted CE-04; here it stays silent.

Not to scale
The problem
  • CE-04 quotation submitted on Wednesday 2 June 2027.
  • No reply. The Contractor notifies the failure on Monday 21 June 2027.
  • Still no reply after that.
Step 1 of 2

Reply due

How many days after the quotation was a reply due?

Two weeks: 14 days, so 16 June.

To the notice
19
To acceptance
33 (19 + 14)
To the notice
19
To acceptance
33 (19 + 14)
Step 2 of 2

Accepted

How many days after the quotation is it treated as accepted?

21 June is 19 days after 2 June; plus 14 is 33 days, so 5 July.

In short. Two weeks to reply, then a notice, then two more weeks. Every day before the notice is a day of waiting added.

Check yourself

Question 1 of 2

The reply period ended yesterday. What should the Contractor do?

  • Right. That starts the two weeks of 62.6.

  • Silence alone is not acceptance.

  • That restarts the reply period and loses time.

Question 2 of 2

A quotation is sent on day 0. The failure notice goes on day 20. On which day is it treated as accepted?

Day 20 + 14 = day 34.

Read the source

Free official texts. The lecture cites clause numbers and puts the rules in its own words.