OpenConstruction Academy
Sign in / Register
EN

Theory before task 1 · 9 min

Landed cost: the price that reaches the deck

Three quotes, one order: landed cost

Course introduction

After this lecture you can

  1. Read what a reinforcement quote includes: bar, cutting and bending, delivery.
  2. Rule out a quote that cannot meet the date the programme needs.
  3. Compare the rest on landed cost and raise the purchase order.
1 / 4

What a rebar quote prices

Slab reinforcement is bought as a bar schedule: high-yield bar to BS 4449, cut and bent to the shapes and lengths the engineer's schedule gives, scheduled to BS 8666. One supplier prices the tonne with cutting and bending in; another adds it as a second rate. Delivery may be free, per tonne or per load. Until you know what each rate covers, the rates cannot be compared.

Example. On this job the deck steel is one schedule from three suppliers, and no two quotes are built the same way.
2 / 4

Landed cost

Landed cost is what it takes to have the material on site, in the form the fixers can use: tonnes times the bar rate, plus processing, plus delivery. VAT stays out, because your firm reclaims it. Build each quote to the same landed cost before you look for the lowest.

Example. A 5 t schedule from a supplier who charges cutting and bending on top.
£4,175
  • Bar, 5 t at £835 £4,175
  • Cutting and bending, 5 t at £110 £550
  • Delivery, free £0
3 / 4

A price that misses the date is not a price

The programme sets the day the steel must be on the deck. A quote that arrives after it is out, however cheap: the fixing gang, the formwork hire and the pour date all wait for it. Rule out the late quotes first, then compare landed cost among the rest.

Example. Three days of a four-person fixing gang standing costs more than most steel savings.
Common mistake

Choosing the lowest headline rate

The lowest £/t on the page is the one most often picked and most often wrong. It may leave cutting and bending out, add delivery, or arrive late. Read every quote down to landed cost and the delivery date before choosing.

Example. A supplier at £20/t less can be dearer once its £110/t processing charge is added.

Mesh for the ground-floor slab

Same job, a different order: the A393 mesh for the ground-floor slab.

Not to scale
The problem
  • Mesh needed: 3.4 t, on site by the Monday the slab is fixed.
  • Supplier A: £960 per tonne, delivered free, on time.
  • Supplier B: £890 per tonne plus £140 per load, on time.
Step 1 of 3

Supplier A

What does supplier A cost on site?

3.4 × £960 = £3,264.00.

Step 2 of 3

Supplier B

What does supplier B cost on site?

3.4 × £890 + £140 = £3,166.00.

Step 3 of 3

The saving

How much cheaper is the better quote?

£3,264.00 − £3,166.00 = £98.00.

In short. Bring every quote to landed cost on the same quantity, among those on time; then the lowest wins.

Check yourself

Question 1 of 2

Which quote do you compare first?

  • Headline rates leave out processing and delivery.

  • Right.

  • Habit is not a comparison.

  • Free delivery can hide a higher rate.

Question 2 of 2

2.5 t of bar at £880/t, cutting and bending £95/t, delivery £150 per load. What is the landed cost?

2.5 × 975 + 150 = £2,587.50.

Read the source

Free official texts. The lecture cites clause numbers and puts the rules in its own words.