What a rebar quote prices
Slab reinforcement is bought as a bar schedule: high-yield bar to BS 4449, cut and bent to the shapes and lengths the engineer's schedule gives, scheduled to BS 8666. One supplier prices the tonne with cutting and bending in; another adds it as a second rate. Delivery may be free, per tonne or per load. Until you know what each rate covers, the rates cannot be compared.