Theory before task 5 · 10 min

A labour-only subcontract order: reverse charge and CIS

The fixing package: reverse charge

After this lecture you can

  1. Decide when the VAT domestic reverse charge applies to a subcontract.
  2. Work out the VAT the contractor accounts for to HMRC.
  3. Explain the CIS deduction that applies to the same payment.
1 / 5

Supply-and-fix, or labour only

Splitting the steel from its fixing is common on UK frames: the main contractor buys the steel and lets a labour-only package to a fixing gang, priced per tonne fixed. The package is a construction contract under the Construction Act, so its payment terms follow sections 109 to 111, and it is a construction service for VAT and CIS.

Example. Two suspended slabs, one fixing gang, one rate per tonne.
2 / 5

Who accounts for the VAT

When the reverse charge applies, the subcontractor's invoice shows the VAT rate and the words that the customer must account for the VAT, but no VAT amount. You enter the VAT on your own return as output tax and, if you can recover it, as input tax in the same return. The net effect is usually nil; the obligation is not.

Example. A blockwork labour package on the same job.
Invoice net, no VAT charged£8,400.00
Output VAT you declare£1,680.00
Input VAT you reclaim−£1,680.00
Net VAT effect£0.00
3 / 5

When it does not apply

The reverse charge is switched off when the customer is the end user (the client building for its own use) or an intermediary that passes the work on to a connected end user and has said so in writing. A main contractor buying a subcontract for the client's building is neither, so the reverse charge applies.

Example. The health partnership buying direct would pay VAT the normal way.
4 / 5

CIS on the same payment

The Construction Industry Scheme makes the contractor deduct tax from the labour part of each payment to a subcontractor and pay it to HMRC: 20 % if the subcontractor is registered, 30 % if not, nothing with gross payment status. Materials the subcontractor buys are left out of the deduction. The ERP order holds the price; the deduction is made on each payment.

Example. On a labour-only package nearly all of each payment is labour.
Common mistake

Reading the reverse charge as 'no VAT'

The invoice shows no VAT, so the order is set to nil and nothing reaches the VAT return. HMRC sees a contractor that did not declare output tax on its construction purchases. The reverse charge moves the VAT; it does not remove it.

Example. Nil on the order, the full rate on your return.

Blockwork labour package

Same job, a different package: laying the ground-floor blockwork.

Not to scale
The problem
  • 300 m² of blockwork laid at £28 per m², the subcontractor's own mortar included.
  • Of that, £1,200 is materials.
  • Subcontractor registered for VAT and CIS; reverse charge applies.
Step 1 of 3

Package net

What is the package net?

300 × £28 = £8,400.00.

Step 2 of 3

Reverse-charge VAT

What VAT do you account for?

£8,400.00 × 20 % = £1,680.00.

Step 3 of 3

CIS deduction

What CIS do you deduct at 20 % on the labour?

(£8,400.00 − £1,200) × 20 % = £1,440.00.

In short. No VAT on the order, VAT on your return; CIS on the labour part of each payment.

Check yourself

Question 1 of 2

A fixing subcontractor's invoice shows no VAT amount. What do you do?

  • The VAT has moved to you.

  • Right.

  • Under the reverse charge it must not.

  • The client is the end user.

Question 2 of 2

A labour-only package is £4,600 net under the reverse charge. What VAT do you account for?

4,600 × 20 % = £920.00.

Read the source