OpenConstruction Academy
Sign in / Register
EN

Theory before task 4 · 9 min

Three-way match: order, receipt, invoice

Three-way match before you pay

After this lecture you can

  1. Match a supplier invoice to its order and confirmed receipt.
  2. Enter an invoice as billed and hold what is not supported.
  3. Work out the amount to approve, VAT included.
1 / 4

Three documents, one question each

The purchase order says what you agreed to buy and at what rate. The goods receipt says what arrived. The invoice says what the supplier asks you to pay. You pay what all three support: the received quantity at the ordered rate. When they disagree, the difference is held, not paid and argued about later.

Example. The block order on the same job: invoiced as ordered, received two pallets short.
Ordered
£7,440
Received
£6,820
Invoiced
£7,440
2 / 4

Enter as billed, hold the difference

The invoice is the supplier's document and must match the copy in its ledger. Enter it exactly as billed and linked to the order; the ERP shows where it exceeds what was received. Approve the supported amount and ask the supplier for a credit note, or for the missing goods, for the rest.

Example. A typed-over invoice hides the dispute from both sides.
3 / 4

Pay on time, dispute on time

Between businesses, a debt paid late carries statutory interest under the Late Payment of Commercial Debts (Interest) Act 1998 unless the contract gives a substantial remedy of its own. That is a reason to tell the supplier promptly what is held and why, not a reason to pay what was not received.

Example. Approve the supported part now; write to the supplier the same day.
Common mistake

Paying because the order says so

An invoice that matches the order looks right, and two-way matching (order against invoice) passes it. Only the receipt shows the bundle that never came. Skip the third document and you pay for steel you did not get.

Example. Order and invoice agree; the receipt is the one that disagrees.

The block invoice

Same job, the block order from the receiving lecture.

Not to scale
The problem
  • Order: 24 pallets at £310, delivery £65.
  • Confirmed receipt: 22 pallets and the delivery.
  • Invoice: 24 pallets and the delivery, VAT 20%.
Step 1 of 2

Supported net

What net value do order and receipt support?

22 × £310 + £65 = £6,885.00.

Step 2 of 2

Approve

What do you approve, VAT included?

£6,885.00 × 1.20 = £8,262.00.

In short. Approve the received quantity at the order rate, with its VAT; hold the rest and ask for a credit.

Check yourself

Question 1 of 2

Order and invoice agree; the receipt is lower. What do you approve?

  • That pays for goods not received.

  • Right.

  • Pay what is supported, on time.

  • VAT is part of what you pay.

Question 2 of 2

Received 18 m³ of concrete ordered at £135/m³; invoiced 20 m³. VAT 20 %. What do you approve?

18 × 135 × 1.20 = £2,916.00.

Read the source

Free official texts. The lecture cites clause numbers and puts the rules in its own words.