Three documents, one question each
The purchase order says what you agreed to buy and at what rate. The goods receipt says what arrived. The invoice says what the supplier asks you to pay. You pay what all three support: the received quantity at the ordered rate. When they disagree, the difference is held, not paid and argued about later.