Cheat sheet

MEP estimating: electrical and HVAC takeoff and bid (US)

Every rule of the course on one page: how each figure is built, the mistake people usually make, and where it comes up at work. Print it or keep it open while you work.

Task 1

Electrical takeoff: count the devices

Theory (9 min)
Rule
'Same as' is not empty. A room drawn 'same as Exam 1' holds the devices of Exam 1: count the typical room once, then multiply.
How it is built
  • Duplex receptacles, count = Duplex in Exam 1 × the exam rooms + Duplex in the other rooms
Usual mistake
Exam rooms 2 to 4 are 'same as Exam 1': their devices count too.
At work
Every electrical bid starts with counts like these; the general contractor's estimator checks the repeated rooms first.

Task 2

Electrical takeoff: conduit and wire for circuit A-7

Theory (9 min)
Rule
Conduit has height. The plan gives the run; the rise to the ceiling and a drop to every box are yours to add, then waste once.
How it is built
  • Vertical conduit, circuit A-7 = Rise from the top of the panelboard to the run + One drop from the run to each box
  • Conduit with drops and waste = Horizontal run from the plan + Vertical conduit × 1.10 for waste
  • Wire with make-up and waste = Conduit before waste × 3 conductors + 1 ft make-up per conductor at each box × 1.10 for waste
Usual mistake
Measure the vertical pieces too: the panel rise and a drop for each box.
At work
Every electrical bid measures runs like these; forget the drops and you lose money on every floor.

Task 3

Price the electrical with labor units

Theory (9 min)
Rule
Hours are not dollars. Rate = hours × crew rate + material; the hours total is kept apart, lump sums included.
How it is built
  • Electrical labor hours, total = Each line: quantity × hours per unit + Conduit and wire: hours per 100 ft ÷ 100 + The hours inside lump 26.08
  • Unit rate of a line = Hours per unit × crew rate + Material per unit
Usual mistake
The units for conduit and wire are per 100 ft: divide by 100.
At work
Electrical estimators price from labor units every day, and the project manager staffs the job from the hours total you hand over.

Task 4

Ductwork: weight by gauge

Theory (9 min)
Rule
Duct is priced by the pound, not by the square foot. Gauge by the longest side; fittings weigh too.
How it is built
  • Duct weight with fittings = Straight duct weight + Fittings weight
  • Weight of one segment = 2 × (W + H) × length ÷ 12 × lb/ft² of the gauge for its longest side
  • Duct labor hours = Duct weight with fittings × 0.08 hr per lb
Usual mistake
Area is not weight: multiply each area by the weight of its gauge.
At work
HVAC estimators weigh every duct run this way; the shop's fabrication order and the field crew's hours both follow the pounds.

Task 5

Build the MEP bid: burden, tax, markups, bond

Theory (10 min)
Rule
Each layer has its own base. Burden and tools follow wages, tax follows material, overhead follows cost, profit and bond follow the running price.
How it is built
  • Base labor, all trades = Electrical hours × electrician rate + Duct hours × sheet metal rate + Piping hours × pipefitter rate
  • Taxable material = Electrical material, lump 26.08 included + Duct material by the pound + HVAC equipment and piping material you buy
  • Bid price = Direct cost: lines, burden, tools and tax + Overhead 9 % + Profit 6 % on the running total + Bond 1.25 % on the running total
Usual mistake
The controls and balancing quotes already carry their tax.
At work
Every subcontract bid is built in these layers, and the GC's estimator checks each base before carrying your number.

Task 6

Price the change order from RFI 14

Theory (8 min)
Rule
Net the change first, then add the terms once. The credit shrinks the base; the change carries its own overhead and profit and no bond.
How it is built
  • Change order price = Change order cost: direct, burden, tools and tax + Overhead and profit, 10 % on the cost
  • Change order direct cost = Added labor hours × rates, net of the deleted + Added material, net of the deleted
  • Net duct weight = Added duct weight − Deleted segment D × 1.30 for fittings
Usual mistake
Changes carry 10 % combined, not the bid markups.
At work
On every job RFIs turn into bulletins and bulletins into change orders; you price each one at the bid's own rates.