Cheat sheet
MEP estimating: electrical and HVAC takeoff and bid (US)
Every rule of the course on one page: how each figure is built, the mistake people usually make, and where it comes up at work. Print it or keep it open while you work.
- Rule
- 'Same as' is not empty. A room drawn 'same as Exam 1' holds the devices of Exam 1: count the typical room once, then multiply.
- How it is built
- Duplex receptacles, count = Duplex in Exam 1 × the exam rooms + Duplex in the other rooms
- Usual mistake
- Exam rooms 2 to 4 are 'same as Exam 1': their devices count too.
- At work
- Every electrical bid starts with counts like these; the general contractor's estimator checks the repeated rooms first.
- Rule
- Conduit has height. The plan gives the run; the rise to the ceiling and a drop to every box are yours to add, then waste once.
- How it is built
- Vertical conduit, circuit A-7 = Rise from the top of the panelboard to the run + One drop from the run to each box
- Conduit with drops and waste = Horizontal run from the plan + Vertical conduit × 1.10 for waste
- Wire with make-up and waste = Conduit before waste × 3 conductors + 1 ft make-up per conductor at each box × 1.10 for waste
- Usual mistake
- Measure the vertical pieces too: the panel rise and a drop for each box.
- At work
- Every electrical bid measures runs like these; forget the drops and you lose money on every floor.
- Rule
- Hours are not dollars. Rate = hours × crew rate + material; the hours total is kept apart, lump sums included.
- How it is built
- Electrical labor hours, total = Each line: quantity × hours per unit + Conduit and wire: hours per 100 ft ÷ 100 + The hours inside lump 26.08
- Unit rate of a line = Hours per unit × crew rate + Material per unit
- Usual mistake
- The units for conduit and wire are per 100 ft: divide by 100.
- At work
- Electrical estimators price from labor units every day, and the project manager staffs the job from the hours total you hand over.
- Rule
- Duct is priced by the pound, not by the square foot. Gauge by the longest side; fittings weigh too.
- How it is built
- Duct weight with fittings = Straight duct weight + Fittings weight
- Weight of one segment = 2 × (W + H) × length ÷ 12 × lb/ft² of the gauge for its longest side
- Duct labor hours = Duct weight with fittings × 0.08 hr per lb
- Usual mistake
- Area is not weight: multiply each area by the weight of its gauge.
- At work
- HVAC estimators weigh every duct run this way; the shop's fabrication order and the field crew's hours both follow the pounds.
- Rule
- Each layer has its own base. Burden and tools follow wages, tax follows material, overhead follows cost, profit and bond follow the running price.
- How it is built
- Base labor, all trades = Electrical hours × electrician rate + Duct hours × sheet metal rate + Piping hours × pipefitter rate
- Taxable material = Electrical material, lump 26.08 included + Duct material by the pound + HVAC equipment and piping material you buy
- Bid price = Direct cost: lines, burden, tools and tax + Overhead 9 % + Profit 6 % on the running total + Bond 1.25 % on the running total
- Usual mistake
- The controls and balancing quotes already carry their tax.
- At work
- Every subcontract bid is built in these layers, and the GC's estimator checks each base before carrying your number.
- Rule
- Net the change first, then add the terms once. The credit shrinks the base; the change carries its own overhead and profit and no bond.
- How it is built
- Change order price = Change order cost: direct, burden, tools and tax + Overhead and profit, 10 % on the cost
- Change order direct cost = Added labor hours × rates, net of the deleted + Added material, net of the deleted
- Net duct weight = Added duct weight − Deleted segment D × 1.30 for fittings
- Usual mistake
- Changes carry 10 % combined, not the bid markups.
- At work
- On every job RFIs turn into bulletins and bulletins into change orders; you price each one at the bid's own rates.