Course introduction · 3 min
Cost control at month 6: earned value and CVR
Mixed-use building, 6 storeys · Month 6 cost report · Fictional project
You are the contractor's quantity surveyor on a six-storey mixed-use building under a FIDIC Red Book contract. Six months in, the board asks whether the job is losing money. In five tasks you write the month 6 cost report: the right baseline, the plan, honest progress and cost, the outturn, and the margin that is left.
- Job
- Mixed-use building, 6 storeys, month 6 of 18
- Contract
- FIDIC Red Book 2017, remeasurement, US dollars
- Method
- Earned value after ISO 21508, then a cost-value reconciliation
- Work in the ERP
- 5 tasks, about 1 h 40 min
Who hands what to whom
Every arrow is a figure that reaches your desk or leaves it, and the task where that happens.
Comes to you
- PlannerCost-loaded programme
- Planned valueTask 2
- Site managerMeasures progress
- Measured %Task 3
Goes from you
- The outturnTask 4
- The forecast marginTask 5
Your route through the job
One monthly report, built in the order a cost engineer builds it. Every task is free.
Measure
Task 1 · 10 min
Budget at completion: cost, not the tender sum
- You produce
- The budget at completion
- Document
- Cost baseline
- In the ERP
- Earned Value
Measure
Task 2 · 20 min
Planned value at the month 6 data date
- You produce
- Planned value at month 6
- Document
- Cost-loaded programme
- In the ERP
- Earned Value
Measure
Task 3 · 25 min
Earned value and actual cost
- You produce
- Earned value and actual cost
- Document
- Progress and ledger
- In the ERP
- Earned Value
Forecast
Task 4 · 20 min
CPI, SPI and the outturn
- You produce
- CPI, SPI, outturn and VAC
- Document
- Monthly cost report
- In the ERP
- Earned Value
Reconcile
Task 5 · 25 min
Cost-value reconciliation and the forecast margin
- You produce
- Value, margin and forecast margin
- Document
- CVR
- In the ERP
- Cost-Value Reconciliation
How one report answers 'is the job losing money?'
Each step below is one task, in the order the report is built.
Blue is what the task adds; grey is carried over from before.
In short. Measure cost against cost, earn at budget, cost the same work, forecast from performance, and value at contract prices.