Course introduction · 3 min

Cost control at month 6: earned value and CVR

Mixed-use building, 6 storeys · Month 6 cost report · Fictional project

You are the contractor's quantity surveyor on a six-storey mixed-use building under a FIDIC Red Book contract. Six months in, the board asks whether the job is losing money. In five tasks you write the month 6 cost report: the right baseline, the plan, honest progress and cost, the outturn, and the margin that is left.

Start task 1

Job
Mixed-use building, 6 storeys, month 6 of 18
Contract
FIDIC Red Book 2017, remeasurement, US dollars
Method
Earned value after ISO 21508, then a cost-value reconciliation
Work in the ERP
5 tasks, about 1 h 40 min

Who hands what to whom

Every arrow is a figure that reaches your desk or leaves it, and the task where that happens.

Comes to you

  • PlannerCost-loaded programme
    • Planned valueTask 2
  • Site managerMeasures progress
    • Measured %Task 3
YouContractor's quantity surveyor

Goes from you

    • The outturnTask 4
    • The forecast marginTask 5
    Main contractorThe board reads the report

Your route through the job

One monthly report, built in the order a cost engineer builds it. Every task is free.

  1. Measure

    Task 1 · 10 min

    Budget at completion: cost, not the tender sum

    You produce
    The budget at completion
    Document
    Cost baseline
    In the ERP
    Earned Value
  2. Measure

    Task 2 · 20 min

    Planned value at the month 6 data date

    You produce
    Planned value at month 6
    Document
    Cost-loaded programme
    In the ERP
    Earned Value
  3. Measure

    Task 3 · 25 min

    Earned value and actual cost

    You produce
    Earned value and actual cost
    Document
    Progress and ledger
    In the ERP
    Earned Value
  4. Forecast

    Task 4 · 20 min

    CPI, SPI and the outturn

    You produce
    CPI, SPI, outturn and VAC
    Document
    Monthly cost report
    In the ERP
    Earned Value
  5. Reconcile

    Task 5 · 25 min

    Cost-value reconciliation and the forecast margin

    You produce
    Value, margin and forecast margin
    Document
    CVR
    In the ERP
    Cost-Value Reconciliation

How one report answers 'is the job losing money?'

Each step below is one task, in the order the report is built.

Mark-upsCost
Task 1BaselineNet cost only; mark-ups outside.
LaterPlanned
Task 2PlanThe budget laid out in time.
BehindEarned
Task 3Earned and spentProgress at budget; cost with accruals.
OverrunBudget
Task 4OutturnForecast from today's efficiency.
MarginCost
Task 5MarginValue against cost, now and at the end.

Blue is what the task adds; grey is carried over from before.

In short. Measure cost against cost, earn at budget, cost the same work, forecast from performance, and value at contract prices.