A tender in two parts
A contractor's tender is the net cost of the work, measured items, preliminaries and provisional sums, plus mark-ups for head office overheads, risk and profit. Earned value measures the work, so the baseline holds the net cost only. Its total is the budget at completion (BAC).
- Measured work $2,300,000
- Preliminaries $420,000
- Provisional sums $280,000
- Mark-ups $450,000