Theory before task 1 · 8 min

The cost baseline and what stays outside it

Budget at completion: cost, not the tender sum

Course introduction

After this lecture you can

  1. Say what the performance measurement baseline holds.
  2. Separate net cost from the mark-ups in a tender.
  3. Work out the budget at completion from a tender build-up.
1 / 3

A tender in two parts

A contractor's tender is the net cost of the work, measured items, preliminaries and provisional sums, plus mark-ups for head office overheads, risk and profit. Earned value measures the work, so the baseline holds the net cost only. Its total is the budget at completion (BAC).

Example. A warehouse tendered at 3,450,000 with 3,000,000 of net cost has a BAC of 3,000,000.
$2,300,000
  • Measured work $2,300,000
  • Preliminaries $420,000
  • Provisional sums $280,000
  • Mark-ups $450,000
2 / 3

Risk allowance is reserve

Money for risks nobody has met yet has no work and no dates, so nothing can be planned or earned against it. ISO 21508 keeps such management reserve outside the baseline. It moves in only when a real, newly found piece of work needs a budget.

Example. If the risk allowance sat in the BAC, every percent complete would be understated from the first month.
Common mistake

Measuring cost against the price

The tender sum is the number everyone knows, so it ends up in the BAC field. Cost is then compared with a budget that includes profit, the CPI looks better than it is, and the overrun appears only when the profit is gone.

Example. Ask of each layer: is there planned work behind it? Only then is it baseline.

BAC from a tender build-up

Different numbers from your task.

Not to scale
The problem
  • Measured work $2,300,000; preliminaries $420,000; provisional sums $280,000.
  • Overheads, risk allowance and profit together $450,000.
Step 1 of 1

Net cost

What is the budget at completion?

$2,300,000 + $420,000 + $280,000 = $3,000,000.

In short. The baseline is the net cost of the work; mark-ups stay on top.

Check yourself

Question 1 of 3

Where does the profit mark-up sit?

  • Right. Profit pays for no work, so it earns nothing.

  • Then the CPI would compare cost with price.

  • In this tender the rates stay net; mark-ups are added once.

Question 2 of 3

A provisional sum for lifts is not yet instructed. Is it in the BAC?

  • Right. Adjust the baseline when the instruction changes the work.

  • It is in the programme and the price; leaving it out distorts every index.

  • Payment has nothing to do with the baseline.

Question 3 of 3

Measured work 1,800,000, preliminaries 310,000, provisional sum 150,000, mark-ups 270,000. What is the BAC?

1,800,000 + 310,000 + 150,000 = 2,260,000.