Theory before task 2 · 8 min

Planned value from a cost-loaded programme

Planned value at the month 6 data date

After this lecture you can

  1. Say what planned value measures.
  2. Spread an activity's budget over its months.
  3. Add up planned value at a data date.
1 / 3

The budget, laid out in time

Planned value (PV) is the budget of the work scheduled to be done by the data date. It comes from the programme with each activity's budget loaded onto it. Here each activity spends evenly over its months; real programmes may load by resource or by quantity.

Example. An activity of 600,000 over months 3 to 8 is planned at 100,000 a month; by the end of month 5 it has 300,000 of planned value.
Groundworks, months 1-2
$180,000
Frame, months 3-8, three months in
$600,000 ($300,000 + $300,000)
2 / 3

Count the activity's own months

An activity that started this month has one month of its plan behind it at the month end. One that starts next month has none. Count from each activity's start, not from the start of the contract.

Example. A 10-month activity starting in month 5 has 2 tenths of its budget planned at the end of month 6.
Common mistake

A straight line over the contract

Dividing the whole budget by the contract months assumes every month costs the same. A frame month costs many finishes months, so a straight line misstates planned value, and the schedule index with it.

Example. Use the programme even when a straight line looks close: next month it will not be.

Planned value of three activities

Different numbers from your task.

Not to scale
The problem
  • Set-up $240,000 over months 1-12; frame $600,000 over months 3-8; services $900,000 over months 5-14.
  • The data date is the end of month 5.
Step 1 of 1

Planned value

What is the planned value at the end of month 5?

100,000 + 300,000 + 90,000 = $490,000.

In short. Planned value: activity by activity, from each activity's own start.

Check yourself

Question 1 of 3

An activity starts next month. Its planned value today is...

  • Right. Its first month is still ahead.

  • Not until its first month ends.

  • Planned value follows the activity, not the contract.

Question 2 of 3

Why load the budget onto the programme instead of the calendar?

  • Right. A frame month is not a painting month.

  • The calendar is fine; it just carries no cost.

  • It is about measuring, not about the client.

Question 3 of 3

An activity of 420,000 runs months 4 to 9. What is its planned value at the end of month 6?

420,000 × 3 ÷ 6 = 210,000.

Read the source