Theory before task 3 · 9 min

Earned value and actual cost of the same work

Earned value and actual cost

After this lecture you can

  1. Say why earned value is a budget and not a cost.
  2. Earn an activity from its measured progress.
  3. Build actual cost from the ledger and accruals.
1 / 3

Three figures, one picture

Planned value is the budget of the work scheduled; earned value (EV) is the budget of the work actually done; actual cost (AC) is what that work cost. EV is compared with PV for schedule and with AC for cost, so EV must never be built from either.

Example. A 500,000 activity measured 40 % complete has earned 200,000, whatever it cost and whatever was planned.
Planned value
$250,000
Earned value
$200,000
Actual cost
$215,000
2 / 3

Same work, same month

The ledger books invoices when they arrive. Goods and work received before the data date but not yet invoiced are accrued, so the cost covers the same work as earned value. Orders for goods not yet delivered are commitments: cost still to come, not cost incurred.

Example. Concrete poured on 28 October with an invoice dated 6 November is October cost.
+$900,0001+$45,0002$945,0003
  • 1 Booked
  • 2 Accruals
  • 3 Actual cost
Common mistake

Taking the ledger as it is

The ledger is built for the books and the bank. Without the accruals the CPI looks fine until the invoices land, and the month they land looks like a disaster.

Example. Agree the list of goods received, not invoiced with the site and accounts before the report goes out.

Earned value and actual cost

Different numbers from your task.

Not to scale
The problem
  • Activity A budget $500,000, 40% complete; activity B budget $300,000, 100% complete.
  • Ledger booked $690,000; received, not invoiced $45,000; an order of 120,000 not delivered.
Step 1 of 2

Earned value

Earned value of A and B?

200,000 + 300,000 = $500,000.

Step 2 of 2

Actual cost

Actual cost?

$690,000 + $45,000 = $735,000.

In short. Earned value is budget × progress; actual cost is booked plus accrued, never commitments.

Check yourself

Question 1 of 3

An activity cost more than planned. Does that raise its earned value?

  • Right. That independence is what makes the CPI mean something.

  • Then EV would equal AC and the CPI would always be 1.

  • The rule is the same for every activity.

Question 2 of 3

Missing accruals make the CPI...

  • Right. Less cost against the same earned value.

  • Less cost raises the CPI.

  • Actual cost is the CPI's divisor.

Question 3 of 3

Budget 350,000, 30 % complete. Earned value?

350,000 × 30 % = 105,000.