Two indices
CPI = EV ÷ AC: the budget earned per unit of money spent. SPI = EV ÷ PV: the work done against the plan, in money. Below 1 means over cost or behind plan. SPI weighs work by cost, so it warns about delay but does not give dates; the programme does.