Theory before task 4 · 9 min

Indices and the outturn

CPI, SPI and the outturn

After this lecture you can

  1. Compute CPI and SPI and say what each measures.
  2. Forecast the outturn by three methods and name their assumptions.
  3. Report the variance at completion with its sign.
1 / 3

Two indices

CPI = EV ÷ AC: the budget earned per unit of money spent. SPI = EV ÷ PV: the work done against the plan, in money. Below 1 means over cost or behind plan. SPI weighs work by cost, so it warns about delay but does not give dates; the programme does.

Example. EV 800,000, AC 880,000, PV 950,000: CPI 0.909, SPI 0.842.
2 / 3

Three outturns, three assumptions

remaining: AC + (BAC − EV), the overrun so far was a one-off. cpi: BAC ÷ CPI, today's cost efficiency continues. combined: AC + (BAC − EV) ÷ (CPI × SPI), the delay keeps costing. A report names the method it headlines and may show the others as the range.

Example. With BAC 2,000,000, EV 800,000 and AC 880,000, the cpi method forecasts 2,200,000.
BAC$2,000,000
CPI = EV ÷ AC0.91
EAC by cpi = BAC ÷ CPI$2,200,000
VAC = BAC − EAC−$200,000
Common mistake

Dividing by the rounded index

A CPI shown to three decimals is rounded. Dividing a multi-million budget by it moves the outturn by thousands. Read the outturn from the measure, which divides by the exact ratio, and only then take the variance.

Example. BAC 2,000,000 ÷ 0.909 gives 2,200,220, not 2,200,000.

Outturn and variance

Different numbers from your task.

Not to scale
The problem
  • BAC $2,000,000, EV $800,000, AC $880,000.
  • Company rule: outturn by the cpi method.
Step 1 of 2

Outturn

EAC by the cpi method?

$2,000,000 × $880,000 ÷ $800,000 = $2,200,000.

Step 2 of 2

Variance

Variance at completion?

$2,000,000 − $2,200,000 = −$200,000.

In short. Outturn by the agreed method; VAC = BAC − EAC, negative when over.

Check yourself

Question 1 of 3

CPI 0.92 and SPI 1.03. The job is...

  • Right.

  • SPI above 1 is ahead; CPI below 1 is over cost.

  • Both indices are away from 1.

Question 2 of 3

The outturn is above the budget at completion. VAC is...

  • Right. VAC = BAC − EAC.

  • Check the order: budget less outturn.

  • VAC is a forecast; it exists from the first measure.

Question 3 of 3

BAC 1,000,000, EV 400,000, AC 500,000. VAC by the cpi method?

EAC = 1,000,000 ÷ 0.8 = 1,250,000; VAC = 1,000,000 − 1,250,000 = −250,000.

Read the source

Free official texts. The lecture cites clause numbers and puts the rules in its own words.