Theory before task 5 · 9 min

Cost-value reconciliation and the forecast margin

Cost-value reconciliation and the forecast margin

After this lecture you can

  1. Say how value in a CVR differs from earned value and from a certificate.
  2. Reconcile value and cost by cost head, with accruals.
  3. Forecast the margin at completion from the outturn.
1 / 3

Two reports, one month

Earned value compares cost with budget: it shows efficiency. A cost-value reconciliation (CVR) compares cost with value, the work done at contract prices: it shows profit. Both use the same progress and the same cost; value adds the mark-ups the client pays for.

Example. Work earned at 1,000,000 of budget, priced with mark-ups of 14 %, has a value of 1,140,000.
$1,060,000
  • Cost and accruals $1,060,000
  • Margin to date $80,000
2 / 3

Value is not the certificate

Under FIDIC the contractor submits a Statement after each month end and the Engineer certifies within 28 days. The amount certified is a month old and is the Engineer's view for payment. The CVR values the work done at the data date, by the contractor's own procedure.

Example. In many countries the CVR goes by another name, a cost report or job cost review; the arithmetic is the same.
Common mistake

Forecasting the margin from the budget

Tender sum less the budget is the margin the tender hoped for. The forecast margin uses the forecast final cost, the outturn. Any forecast overrun comes straight out of the margin.

Example. Tender margin 300,000 and a VAC of −120,000 leave a forecast margin of 180,000.

A CVR in two lines

Different numbers from your task.

Not to scale
The problem
  • Earned value $1,000,000; mark-ups compounded to 1.14.
  • Booked cost $1,010,000; accruals $50,000. Forecast final value $4,560,000; outturn $4,260,000.
Step 1 of 3

Value

Value to date?

$1,000,000 × 1.14 = $1,140,000.

Step 2 of 3

Margin

Margin to date?

$1,140,000 − $1,010,000 − $50,000 = $80,000.

Step 3 of 3

Forecast

Forecast margin?

$4,560,000 − $4,260,000 = $300,000.

In short. Value at contract prices; cost with accruals; forecast margin from the outturn.

Check yourself

Question 1 of 3

The Engineer certified less than your CVR value. Is your value wrong?

  • Right. Reconcile the gap; do not copy the certificate.

  • The Engineer certifies payment; the CVR is your management view.

  • Work done after the Statement has value before it is certified.

Question 2 of 3

Margin to date is positive but VAC is negative. Which is right?

  • Right. Forecast margin tells the board the end of the story.

  • Today's margin ignores the cost still to come.

  • The CVR adds the profit view the indices lack.

Question 3 of 3

Tender sum 6,000,000; outturn 5,550,000. Forecast margin?

6,000,000 − 5,550,000 = 450,000.