One-way status
A diary is open while the day runs, closed at its end, and signed when the week is checked. Signing seals the content with a fingerprint; later changes show. An archived diary is final.
Theory before task 4 · 7 min
Sign the week; total it for the monthly report
A diary is open while the day runs, closed at its end, and signed when the week is checked. Signing seals the content with a fingerprint; later changes show. An archived diary is final.
FIDIC 4.20 asks for a monthly progress report within 7 days of the period end, with the records of personnel and equipment of 6.10. The report states the resources; the signed diaries prove them. Man-days are the daily labour counts added up.
A wrong count found later is tempting to fix where it is. Unlocking leaves a trail, and the Engineer will ask what else changed. Correct it in today's diary, with the reason.
Different numbers from your task.
Man-days in the week?
Hint: Add the five labour counts; visitors are not labour.
Right.
Its day has not ended.
Archive is final; the day has hardly started.
Right.
That is plant time.
That is a record, not a resource.
Free official texts. The lecture cites clause numbers and puts the rules in its own words.
The records of personnel and equipment the contract asks for each month, and where they go.
Free guidance used worldwide on keeping records that prove delay; see the core principles.
How progress, resources and issues are reported in project management, in any country.