Site diary and daily reports as contract records
On a fictional six-storey mixed-use building under a FIDIC Red Book contract.
Who it's for Site manager

You will be able to
Skills checked
- Count a day's labour return: subcontractors' people included, visitors and delivery drivers left out
- Record plant working and standing, and measure a delay against the planned start
- Keep contemporary records of held labour and plant for a claim (FIDIC 20.2)
- Sign a week of diaries and total the man-days for the monthly progress report (FIDIC 4.20)
- Test rain days against the 10-year climate record for an extension of time (FIDIC 8.5)
Tasks
A task as it opens in the trainer, before you enter anything.

- 1
- 2
- 3
- 4
- 5
Difficulty is calculated from the steps and the figures you check in each task. Time is the median of real learners once enough have finished; until then it is the author's estimate.
Certificate
Awarded when all 5 tasks pass the numbers, trace and explain checks.

What next
Questions about this course? Write to info@datadrivenconstruction.io
Related courses
Your roleEstimatorTender estimate: from net rates to the tender sum
On a fictional six-storey mixed-use building.
Foundation1 h of studyFigures checked 10EN
All 5 tasks freeCertificate of completion
Your roleHealth and safety leadSite safety: risk, permits, incidents and LTIFR
On a fictional six-storey mixed-use building under a FIDIC Red Book contract.
Foundation1.5 h of studyFigures checked 11EN
All 5 tasks freeCertificate of completion
Your roleQuantity surveyor at the client's cost consultantQuantity takeoff from PDF, DWG and IFC
On an invented six-storey mixed-use building.
Foundation1.5 h of studyFigures checked 13EN
All 5 tasks freeCertificate of completion