Course introduction · 3 min
Site diary and daily reports as contract records
Mixed-use building, 6 storeys · Site diary, October · Fictional project
You are the contractor's site manager on a six-storey mixed-use building under a FIDIC Red Book contract. It is October, month 6, and the frame is rising. In five tasks you keep the site diary the way a claim will later need it: the right people and plant, a delay with its times, records of a held bay, a signed week, and the rain days tested against the record.
- Job
- Mixed-use building, 6 storeys, month 6 of 18, frame in progress
- Contract
- FIDIC Red Book 2017: 6.10 records, 4.20 progress reports, 20.2 claims
- Module
- Daily Site Diary
- Work in the ERP
- 5 tasks, about 1 h 30 min
Who hands what to whom
Every arrow is a record that reaches your diary or leaves it, and the task where that happens.
Comes to you
- Concrete frame subcontractorPeople and plant on the frame
- Sign-in registerTask 1
- The EngineerInspects and instructs
- Late inspectionTask 2
- Late drawingTask 3
Goes from you
- Held-bay hoursTask 3
- Rain daysTask 5
Your route through the job
Two weeks of one diary, in the order a site manager meets them. Every task is free.
The day
Task 1 · 10 min
Who counts as labour on the site diary
- You produce
- The labour return
- Document
- Sign-in register
- In the ERP
- Daily Site Diary
The day
Task 2 · 15 min
Plant, visitors and a delay recorded against the plan
- You produce
- Plant return and the delay
- Document
- Diary of the pour day
- In the ERP
- Daily Site Diary
The claim
Task 3 · 25 min
Contemporary records for a claim
- You produce
- Labour-hours and plant-hours held
- Document
- Event entries
- In the ERP
- Daily Site Diary
The week and the month
Task 4 · 20 min
Sign the week; total it for the monthly report
- You produce
- Signed week and man-days
- Document
- Progress report records
- In the ERP
- Daily Site Diary
The week and the month
Task 5 · 20 min
Rain days tested against the climate record
- You produce
- Rain days beyond the record
- Document
- Weather record
- In the ERP
- Daily Site Diary
How a diary becomes evidence
Each step below is one task, in the order the record is built.
Blue is what the task adds; grey is carried over from before.
In short. Write it the same day, count what was there, time it against the plan, sign it weekly, and test weather against the record.