Course introduction · 3 min

Site diary and daily reports as contract records

Mixed-use building, 6 storeys · Site diary, October · Fictional project

You are the contractor's site manager on a six-storey mixed-use building under a FIDIC Red Book contract. It is October, month 6, and the frame is rising. In five tasks you keep the site diary the way a claim will later need it: the right people and plant, a delay with its times, records of a held bay, a signed week, and the rain days tested against the record.

Start task 1

Job
Mixed-use building, 6 storeys, month 6 of 18, frame in progress
Contract
FIDIC Red Book 2017: 6.10 records, 4.20 progress reports, 20.2 claims
Module
Daily Site Diary
Work in the ERP
5 tasks, about 1 h 30 min

Who hands what to whom

Every arrow is a record that reaches your diary or leaves it, and the task where that happens.

Comes to you

  • Concrete frame subcontractorPeople and plant on the frame
    • Sign-in registerTask 1
  • The EngineerInspects and instructs
    • Late inspectionTask 2
    • Late drawingTask 3
YouSite manager

Goes from you

    • Held-bay hoursTask 3
    • Rain daysTask 5
    Contractor's quantity surveyorPrices claims from the records

Your route through the job

Two weeks of one diary, in the order a site manager meets them. Every task is free.

  1. The day

    Task 1 · 10 min

    Who counts as labour on the site diary

    You produce
    The labour return
    Document
    Sign-in register
    In the ERP
    Daily Site Diary
  2. The day

    Task 2 · 15 min

    Plant, visitors and a delay recorded against the plan

    You produce
    Plant return and the delay
    Document
    Diary of the pour day
    In the ERP
    Daily Site Diary
  3. The claim

    Task 3 · 25 min

    Contemporary records for a claim

    You produce
    Labour-hours and plant-hours held
    Document
    Event entries
    In the ERP
    Daily Site Diary
  4. The week and the month

    Task 4 · 20 min

    Sign the week; total it for the monthly report

    You produce
    Signed week and man-days
    Document
    Progress report records
    In the ERP
    Daily Site Diary
  5. The week and the month

    Task 5 · 20 min

    Rain days tested against the climate record

    You produce
    Rain days beyond the record
    Document
    Weather record
    In the ERP
    Daily Site Diary

How a diary becomes evidence

Each step below is one task, in the order the record is built.

EntriesLabour
Task 1PeopleEveryone working on site.
DelayPlanned
Task 2Plant and delayFrom the plan, with times.
StoodWorked
Task 3Claim recordsOnly what the event held.
TodaySigned
Task 4Signed weekSealed close to the event.
ExcessRecord
Task 5WeatherBeyond the record: time.

Blue is what the task adds; grey is carried over from before.

In short. Write it the same day, count what was there, time it against the plan, sign it weekly, and test weather against the record.