A record written for a reader months away
The diary is written by the site manager on the day, but its real reader comes later: the Engineer checking a claim, a quantity surveyor pricing a delay, an adjudicator or arbitrator. FIDIC 6.10 asks for records of each class of personnel and each type of equipment on site, and 4.20 puts them in every monthly progress report.