Theory before task 2 · 8 min

Plant, visitors and a delay on record

Plant, visitors and a delay recorded against the plan

After this lecture you can

  1. Count the plant return, working and standing.
  2. Write visitor, delivery and event entries for the same day.
  3. Measure a delay from the planned start to the actual start.
1 / 3

Standing plant is still plant

A machine on site costs money whether it works or stands. The plant return counts every machine on site and says which stood, and why. Trucks that deliver and leave are deliveries; hand-held tools are not plant.

Example. A crane, a pump and a standing telehandler make three in the return; four concrete trucks are one delivery entry.
2 / 3

A delay has two ends

A delay is measured against the plan: from when the work should have started to when it did. Arrival of a machine, a phone call or a release are events in between. Write each with its time and who was involved: that is what shows whose risk it was.

Example. Planned start 07:00, actual start 08:45: a delay of 1.75 hours, whatever happened in between.
Planned start to actual start
1.75
Machine arrival to actual start
2
Common mistake

Timing from the arrival

The pump arrived early, so the wait looks longer from its arrival. The early part was your own choice. A claim built on it fails at the first question, and the rest of the record is doubted with it.

Example. Count from the planned start, and keep the arrival time in the entry as a fact.

Delay to a start

Different numbers from your task.

Not to scale
The problem
  • Planned start 07:00 (7 h); the inspection came late; actual start 08:45 (8.75 h).
  • The pump was on site from 06:45.
Step 1 of 1

Delay

Delay to the start, in hours?

8.75 − 7 = 1.75 h.

In short. A delay runs from the planned start to the actual start; the events between are its causes.

Check yourself

Question 1 of 3

A telehandler stood all day with no work in its area. In the plant return it is...

  • Right.

  • Standing plant on site is cost.

  • The return counts machines; the state is noted.

Question 2 of 3

Eight concrete trucks delivered during the pour. The diary shows...

  • Right. Trucks come and go.

  • Delivery vehicles are not plant on site.

  • The delivery belongs in the diary of the day.

Question 3 of 3

Planned start 09:00, actual start 12:15. Delay in hours?

12.25 − 9 = 3.25 h.

Read the source

Free official texts. The lecture cites clause numbers and puts the rules in its own words.