Cheat sheet
Site diary and daily reports as contract records
Every rule of the course on one page: how each figure is built, the mistake people usually make, and where it comes up at work. Print it or keep it open while you work.
- Rule
- Labour is everyone working on the site, whoever employs them. Visitors and drivers are entries.
- How it is built
- Labour count = Main contractor's people + Subcontractors' people
- Usual mistake
- Only the main contractor's own people. Every subcontractor's people are Contractor's Personnel too.
- At work
- The site manager copies the labour lines from the register every evening, by trade and by employer.
- Rule
- A delay is recorded from the planned start to the actual start, with who caused it, in the diary of the day.
- How it is built
- Delay to the pour start = Actual start − Planned start
- Usual mistake
- That runs from when the pump arrived. The delay runs from the planned start of the pour.
- At work
- The site manager writes the event entry before the end of the day, with each time and each person.
- Rule
- A claim is only as good as the record of the day. Name what the event held up, and how long.
- How it is built
- Labour-hours on the held bay = People on the bay × Hours stood, both days
- Plant-hours on the held bay = Plant on the bay × Hours stood, both days
- Usual mistake
- The whole frame gang was counted. Only the people on the held bay stood; the rest worked on the west bay.
- At work
- The site manager and the quantity surveyor agree what the event held before the entry is written.
- Rule
- Sign each ended week; correct forward. A signed diary is evidence; an edited one invites questions.
- How it is built
- Man-days, week ending 16 October = Labour, 12 to 14 October + Labour, 15 and 16 October
- Usual mistake
- Today's diary was added. The week ended on Friday.
- At work
- Every Monday the site manager signs the ended week and sends the totals to the quantity surveyor.
- Rule
- Only weather beyond the published record is exceptional, and it buys time, not money.
- How it is built
- Rain days beyond the 10-year record = Gauge days over 10 mm − 10-year record
- Usual mistake
- Those are the days the frame stopped. The test compares rain days at the gauge with the record.
- At work
- The site manager reads the gauge at the same time every day and logs it, worked day or not.