Cheat sheet

Site diary and daily reports as contract records

Every rule of the course on one page: how each figure is built, the mistake people usually make, and where it comes up at work. Print it or keep it open while you work.

Task 1

Who counts as labour on the site diary

Theory (7 min)
Rule
Labour is everyone working on the site, whoever employs them. Visitors and drivers are entries.
How it is built
  • Labour count = Main contractor's people + Subcontractors' people
Usual mistake
Only the main contractor's own people. Every subcontractor's people are Contractor's Personnel too.
At work
The site manager copies the labour lines from the register every evening, by trade and by employer.

Task 2

Plant, visitors and a delay recorded against the plan

Theory (8 min)
Rule
A delay is recorded from the planned start to the actual start, with who caused it, in the diary of the day.
How it is built
  • Delay to the pour start = Actual start − Planned start
Usual mistake
That runs from when the pump arrived. The delay runs from the planned start of the pour.
At work
The site manager writes the event entry before the end of the day, with each time and each person.

Task 3

Contemporary records for a claim

Theory (9 min)
Rule
A claim is only as good as the record of the day. Name what the event held up, and how long.
How it is built
  • Labour-hours on the held bay = People on the bay × Hours stood, both days
  • Plant-hours on the held bay = Plant on the bay × Hours stood, both days
Usual mistake
The whole frame gang was counted. Only the people on the held bay stood; the rest worked on the west bay.
At work
The site manager and the quantity surveyor agree what the event held before the entry is written.

Task 4

Sign the week; total it for the monthly report

Theory (7 min)
Rule
Sign each ended week; correct forward. A signed diary is evidence; an edited one invites questions.
How it is built
  • Man-days, week ending 16 October = Labour, 12 to 14 October + Labour, 15 and 16 October
Usual mistake
Today's diary was added. The week ended on Friday.
At work
Every Monday the site manager signs the ended week and sends the totals to the quantity surveyor.

Task 5

Rain days tested against the climate record

Theory (8 min)
Rule
Only weather beyond the published record is exceptional, and it buys time, not money.
How it is built
  • Rain days beyond the 10-year record = Gauge days over 10 mm − 10-year record
Usual mistake
Those are the days the frame stopped. The test compares rain days at the gauge with the record.
At work
The site manager reads the gauge at the same time every day and logs it, worked day or not.

Back to the course