Site levels: platform, cut and fill, building corners
You are the land surveyor on a fictional 2.4 ha development plot. Groundworks start next week. In five tasks you read the ground from spot levels, put the building platform on it, find the level that needs no lorries, fix the building corners from the boundary and check the crew's stakes.
Fictional project- Plot
- Development plot, five corners, street on the south side
- Coordinates
- Projected grid, metres; levels in metres
- Method
- Ground surface, design pad, cut and fill, polar setting out, stake check
- Work in the ERP
- 5 tasks, about 1 h 52 min
Who hands what to whom
Every arrow is a figure that reaches your desk or leaves it, and the task where that happens.
Comes to you
- Site managerAsks for levels and corners
- FallTask 1
- No lorriesTask 3
- Setting-out crewStakes the corners
- StakesTask 5
Goes from you
- Cut and fillTask 2
- Platform levelTask 3
- SetbackTask 4
Your route through the job
From the ground to the pegs. Every task is free.
Levels
Task 1 · 12 min
Read the ground from spot levels
- You produce
- Fall of the ground
- Document
- Ground surface
- In the ERP
- Volumes
Levels
Task 2 · 25 min
Platform at 412.000: cut and fill
- You produce
- Cut and fill
- Document
- Volume
- In the ERP
- Volumes
Levels
Task 3 · 25 min
The level that balances
- You produce
- Balanced level
- Document
- Volume
- In the ERP
- Volumes
Setting out
Task 4 · 25 min
Corners from the boundary
- You produce
- Building corners
- Document
- Saved points
- In the ERP
- Calculations
Setting out
Task 5 · 25 min
Stake, check and decide
- You produce
- Stake check
- Document
- Setting-out record
- In the ERP
- Setting-out
How the ground becomes a building on pegs
Each step below is one task, in the order the site needs it.
Blue is what the task adds; grey is carried over from before.
In short. Take every level and corner from the one survey, and check every peg against its design.