Course introduction · 3 min
Price, win and vary a FIDIC contract
Mixed-use building, 6 storeys · Shops on the ground floor, offices on level 1, flats on levels 2 to 5. Concrete frame. · Fictional project
You are the main contractor's quantity surveyor on a six-storey mixed-use building under the FIDIC Red Book 2017. In five tasks you price the last blank lines of the tender, build the tender sum, buy the drywall, send the first monthly Statement and value the first variation the Engineer instructs.
- Building
- Shops on the ground floor, offices on level 1, flats on levels 2 to 5. Concrete frame.
- Contract
- FIDIC Red Book 2017, remeasured bill of quantities, USD
- Rules
- FIDIC 1.1, 4.11, 12.3, 13.3.1, 14.3, 14.6, 14.7, 14.9
- Work in the ERP
- 5 tasks, about 1 h 30 min
Who hands what to whom
Every arrow is a figure that reaches your desk or leaves it, and the task where that happens.
Comes to you
- DirectorSigns the tender
- Mark-upsTask 2
- Drywall biddersBidders A, B and C
- BidsTask 3
The EngineerClient's contract administrator- Instruction 01Task 5
YouContractor's quantity surveyorGoes from you
- Tender sumTask 2
- Statement 1Task 4
- Variation proposalTask 5
The EngineerCertifies payment
The project and the people are fictional. Portraits are generated.
Your route through the job
Two tasks win the job, one buys the first package, two run the Contract. Start with task 1: two lines of the bill are blank.
Tender
Task 1 · 10 min
Price the two blank lines before the tender closes
- You produce
- The last two lines priced
- Document
- Estimator's build-up sheet
- In the ERP
- Bill of Quantities
Tender
Task 2 · 15 min
Put the mark-ups on once: the tender sum
- You produce
- The tender sum
- Document
- Director's mark-ups
- In the ERP
- Bill of Quantities
Award
Task 3 · 25 min
Level the drywall bids before you award
- You produce
- The drywall awarded
- Document
- Three bids
- In the ERP
- Bid Management
Contract
Task 4 · 20 min
Interim Payment 1: value May, know the retention limit
- You produce
- Statement 1 and the retention limit
- Document
- Contract Data
- In the ERP
- Contracts
Contract
Task 5 · 20 min
The first variation, at the rates of the Contract
- You produce
- Variation 01 in the contract sum
- Document
- Engineer's instruction 01
- In the ERP
- Variations
One price, carried through the Contract
Each step is one task. The rates you price in the tender are the rates every later figure is valued at.
Blue is what the task adds; grey is carried over from before.
In short. Price every line net. Mark up once. Buy on one scope. Value everything at the rates of the Contract.