Course introduction · 3 min

Price, win and vary a FIDIC contract

Mixed-use building, 6 storeys · Shops on the ground floor, offices on level 1, flats on levels 2 to 5. Concrete frame. · Fictional project

You are the main contractor's quantity surveyor on a six-storey mixed-use building under the FIDIC Red Book 2017. In five tasks you price the last blank lines of the tender, build the tender sum, buy the drywall, send the first monthly Statement and value the first variation the Engineer instructs.

Start task 1

Building
Shops on the ground floor, offices on level 1, flats on levels 2 to 5. Concrete frame.
Contract
FIDIC Red Book 2017, remeasured bill of quantities, USD
Rules
FIDIC 1.1, 4.11, 12.3, 13.3.1, 14.3, 14.6, 14.7, 14.9
Work in the ERP
5 tasks, about 1 h 30 min

Who hands what to whom

Every arrow is a figure that reaches your desk or leaves it, and the task where that happens.

Comes to you

  • DirectorSigns the tender
    • Mark-upsTask 2
  • Drywall biddersBidders A, B and C
    • BidsTask 3
  • The EngineerClient's contract administrator
    • Instruction 01Task 5
YouContractor's quantity surveyor

Goes from you

    • Tender sumTask 2
    ClientDeveloper of the building
    • Statement 1Task 4
    • Variation proposalTask 5
    The EngineerCertifies payment

The project and the people are fictional. Portraits are generated.

Your route through the job

Two tasks win the job, one buys the first package, two run the Contract. Start with task 1: two lines of the bill are blank.

  1. Tender

    Task 1 · 10 min

    Price the two blank lines before the tender closes

    You produce
    The last two lines priced
    Document
    Estimator's build-up sheet
    In the ERP
    Bill of Quantities
  2. Tender

    Task 2 · 15 min

    Put the mark-ups on once: the tender sum

    You produce
    The tender sum
    Document
    Director's mark-ups
    In the ERP
    Bill of Quantities
  3. Award

    Task 3 · 25 min

    Level the drywall bids before you award

    You produce
    The drywall awarded
    Document
    Three bids
    In the ERP
    Bid Management
  4. Contract

    Task 4 · 20 min

    Interim Payment 1: value May, know the retention limit

    You produce
    Statement 1 and the retention limit
    Document
    Contract Data
    In the ERP
    Contracts
  5. Contract

    Task 5 · 20 min

    The first variation, at the rates of the Contract

    You produce
    Variation 01 in the contract sum
    Document
    Engineer's instruction 01
    In the ERP
    Variations

One price, carried through the Contract

Each step is one task. The rates you price in the tender are the rates every later figure is valued at.

Net
Task 1PriceEvery line a net rate.
Mark-upsNet
Task 2TenderMark-ups on once.
Leveled
Task 3BuyLevel, then award.
May
Task 4Get paidStatement, certificate, payment.
Contract sum
Task 5VaryValued at the rates of the Contract.

Blue is what the task adds; grey is carried over from before.

In short. Price every line net. Mark up once. Buy on one scope. Value everything at the rates of the Contract.