Theory before task 1 · 7 min

A remeasured bill: every line needs a net rate

Price the two blank lines before the tender closes

Course introduction

After this lecture you can

  1. Say what a remeasurement contract pays for.
  2. Price a bill line with a net rate.
  3. Explain why a blank rate costs the contractor.
1 / 4

What a remeasured bill is

Under the FIDIC Red Book the Client's designer draws the building and the Client's cost consultant measures it into a bill of quantities. You price each line with a rate. During the job the work actually built is measured again and paid at your rates, so the quantities can move but the rates stay fixed.

Example. On this building the bill has seven sections, from preliminaries to provisional sums.
2 / 4

A net rate and what it holds

In this bill every rate is net: labour, material and plant for one unit, and nothing else. Overheads, risk and profit are added once, over the whole bill, in the next step. Keeping rates net means every line is priced the same way.

Example. Roughly how a partition rate is made: studs, board, labour (rounded).
USD9.40USD17.70USD15.40
  • Studs and track USD9.40
  • Board and jointing USD17.70
  • Fixer's time USD15.40
3 / 4

Why a blank rate is free work

Tender instructions usually say that an item left unpriced is deemed covered by the other rates, and FIDIC deems the accepted price sufficient for everything in the Contract. So a blank line is still built and still measured, but paid at nothing.

Example. Practice differs a little by country, but the deemed-included rule is the common case.
Common mistake

Pricing one line of a section

Two lines are blank and the estimator prices the bigger one, then reads that line as the section. Always read the section row after pricing: it shows whether every line below it carries a rate.

Example. A section total is never one line unless the section has one line.

The suspended ceilings

Same bill, line FIN.02, already priced.

Not to scale
The problem
  • Suspended ceiling, shops and offices: 1,884 m2.
  • Net rate: USD36.00 per m2.
Step 1 of 1

Line total

What is the line total?

1,884 × USD36.00 = USD67,824.00.

In short. Quantity times net rate gives each line; the section adds its lines.

Check yourself

Question 1 of 2

A tender line is left without a rate. Under the usual rules, what happens?

  • Right.

  • The item is deemed covered by other rates.

  • The work is still in the drawings.

  • Nobody else's rate enters your contract.

Question 2 of 2

A floor screed line is 5,580 m2 at 18.00 net. What is its line total?

5,580 × 18.00 = 100,440.