Theory before task 2 · 8 min

From net cost to tender sum

Put the mark-ups on once: the tender sum

After this lecture you can

  1. Add mark-ups once, over the whole bill.
  2. Choose the base of each mark-up.
  3. Know what the tender sum becomes.
1 / 4

Three mark-ups, once

The net bill is what the building costs your firm to build. On top of it go head office overheads, a risk allowance and profit. They are added once, as rows below the bill, so the director can see and change each one without repricing a single line.

Example. The same mark-ups on a round 100,000 (amounts rounded).
Net costUSD100,000.00
Overheads 6 %USD6,000.00
Risk 2.5 % on the running totalUSD2,650.00
Profit 5 % on the running totalUSD5,433.00
Tender sumUSD114,083.00
2 / 4

The base of each row

A mark-up on the sum of positions ignores the rows above it. A mark-up on the running total includes them, so the order of the rows changes the result. Your director's rule: overheads on the net cost, then risk and profit each on the running total.

Example. In the ERP the base is set in Edit calculation.
3 / 4

What the tender sum becomes

If the Client accepts your tender, the Letter of Acceptance names your tender sum as the Accepted Contract Amount. Retention limits, securities and many notices are worked out from it, so it must be right on the day it is sent.

Example. The performance security is due within 28 days of the Letter of Acceptance (4.2).
Common mistake

Adding the percentages

6 + 2.5 + 5 = 13.5 %, taken once on the net cost, is quick and wrong: it leaves out the risk on the overheads and the profit on both. On a large bill the gap is thousands.

Example. Rows on the running total compound; a single percentage does not.

A package of 200,000

The same rule on a round figure.

Not to scale
The problem
  • Net cost USD200,000.
  • Overheads 6 % on it; risk 2.5 % and profit 5 % on the running total.
Step 1 of 2

After overheads

What is the running total after overheads?

USD200,000 × 1.06 = USD212,000.00.

Step 2 of 2

Tender sum

What is the sum after risk and profit?

USD212,000.00 × 1.025 × 1.05 = USD228,165.00.

In short. Each row on the total above it; read the Grand Total.

Check yourself

Question 1 of 2

Profit is set to Sum of positions instead of the running total. What happens?

  • Right.

  • The base decides the amount.

  • It is taken once, on less.

  • Both bases are allowed.

Question 2 of 2

Net cost 50,000; overheads 6 %, then profit 5 % on the running total. Total?

50,000 × 1.06 × 1.05 = 55,650.