Theory before task 3 · 8 min

Level the bids, then award

Level the drywall bids before you award

After this lecture you can

  1. Spot a blank line in a subcontract bid.
  2. Plug it by a stated rule.
  3. Award the lowest complete bid.
1 / 4

Why the low bid has a hole in it

A firm that wants to be low reads the scope narrowly. Here one drywall firm priced the flats and left out the shops and offices: its total is lower because it covers less, not because it is cheaper.

Example. Shops and offices have taller walls and more openings than flats.
2 / 4

The plug

If the missing line cannot be confirmed in time, you price it yourself on the leveling sheet. A cautious rule plugs it at the highest rate another bidder quoted, because an unconfirmed price that turns out higher is an overrun you own.

Example. A ceiling bid that left the bulkheads unpriced (our figures).
Lines the bidder pricedUSD96,000.00
Plug for the blank lineUSD14,400.00
Leveled bidUSD110,400.00
3 / 4

Award the lowest complete bid

Once every bid covers the same lines, compare and award the lowest one that is complete in the ERP, at its own price. Then compare it with the allowance in your tender: the difference is your buying margin.

Example. The award moves the package from bids to a subcontract.
Common mistake

Plugging at the bidder's own rate

It looks fair to price the blank line at the rate the same bidder gave for similar work. But the bidder never priced that work. Its rate for other work tells you nothing about the line it refused.

Example. A plug is a risk allowance, not a guess at a discount.

The ceiling bids

Same job, the suspended ceilings package.

Not to scale
The problem
  • Ceiling bid: USD62,800 for the lines it priced; bulkheads left blank.
  • Other bidders priced bulkheads at USD6,900 and USD5,800.
Step 1 of 1

Leveled

What is the leveled ceiling bid?

USD62,800 + USD6,900 = USD69,700.00.

In short. Plug on the sheet, by the rule, and compare only once every bid covers the same lines.

Check yourself

Question 1 of 2

A bid leaves a mandatory line blank. What goes on the leveling sheet?

  • Right.

  • It becomes your cost.

  • The most optimistic guess.

  • Then the scopes differ.

Question 2 of 2

A bid is 71,500 without one line; others priced it at 4,200 and 3,600. Highest plug: leveled bid?

71,500 + 4,200 = 75,700.