Why the low bid has a hole in it
A firm that wants to be low reads the scope narrowly. Here one drywall firm priced the flats and left out the shops and offices: its total is lower because it covers less, not because it is cheaper.
Theory before task 3 · 8 min
Level the drywall bids before you award
A firm that wants to be low reads the scope narrowly. Here one drywall firm priced the flats and left out the shops and offices: its total is lower because it covers less, not because it is cheaper.
If the missing line cannot be confirmed in time, you price it yourself on the leveling sheet. A cautious rule plugs it at the highest rate another bidder quoted, because an unconfirmed price that turns out higher is an overrun you own.
Once every bid covers the same lines, compare and award the lowest one that is complete in the ERP, at its own price. Then compare it with the allowance in your tender: the difference is your buying margin.
It looks fair to price the blank line at the rate the same bidder gave for similar work. But the bidder never priced that work. Its rate for other work tells you nothing about the line it refused.
Same job, the suspended ceilings package.
What is the leveled ceiling bid?
Hint: Bid as priced plus the highest other price.
Right.
It becomes your cost.
The most optimistic guess.
Then the scopes differ.
Free official texts. The lecture cites clause numbers and puts the rules in its own words.
The main contractor stays responsible for its subcontractors' work under the Contract.
Project management guidance on procurement decisions and the records behind them.