Theory before task 4 · 8 min

Interim payment and retention under FIDIC

Interim Payment 1: value May, know the retention limit

After this lecture you can

  1. Follow a Statement to a payment.
  2. Read the retention rate and limit in the Contract Data.
  3. Work out the retention limit.
1 / 4

The monthly Statement

After each month the contractor sends the Engineer a Statement: the value of the work done to date at the rates of the Contract, less retention and earlier payments. The Engineer certifies what is due in an Interim Payment Certificate.

Example. On this job the first Statement covers 4 to 31 May.
2 / 4

The two clocks

The Engineer has 28 days from receiving the Statement to issue the certificate, and the Client must pay within 56 days of the Engineer receiving it. Late payment carries financing charges under 14.8.

Example. Both clocks start on the same day: when the Statement arrives.
3 / 4

Retention: a rate and a limit

The Contract Data states two figures: the percentage held from each valuation and the limit of Retention Money, a share of the Accepted Contract Amount. Deductions stop once they add up to the limit.

Example. A month of our own figures, not this job's.
Gross valuationUSD120,000.00
Retention 10 %USD12,000.00
Due before earlier paymentsUSD108,000.00
Common mistake

The limit as the monthly rate

The rate (10 %) and the limit (5 %) sit next to each other in the Contract Data and get mixed up. The rate applies to each valuation; the limit applies to the Accepted Contract Amount once.

Example. Rate per month, limit per contract.

A smaller contract

A different contract with the same Contract Data.

Not to scale
The problem
  • Accepted Contract Amount USD2,400,000.
  • Retention 10 %, limit 5 % of the Accepted Contract Amount.
Step 1 of 1

Limit

What is the limit of Retention Money?

USD2,400,000 × 5 % = USD120,000.00.

In short. One limit per contract; monthly deductions add up to it and stop.

Check yourself

Question 1 of 2

The Engineer receives a Statement on 30 June. By when must the Client pay?

  • Right.

  • 28 days is the certificate.

  • The Contract counts days.

  • The period is fixed by 14.7.

Question 2 of 2

Accepted Contract Amount 3,600,000; limit 5 %. What is the limit of Retention Money?

3,600,000 × 5 % = 180,000.

Read the source