Theory before task 5 · 8 min

A variation by instruction, valued at the rates of the Contract

The first variation, at the rates of the Contract

After this lecture you can

  1. Follow a Variation from instruction to contract sum.
  2. Value similar work at the rate of the Contract.
  3. Keep the mark-ups in the valuation.
1 / 4

Variation by instruction

The Engineer may vary the Works at any time before taking-over. The contractor carries out the instruction and, within 28 days, sends detailed particulars: what is done, its effect on the programme and the proposed adjustment to the Contract Price.

Example. Instruction 01 divides the level 1 offices into meeting rooms.
2 / 4

Which rate

Work of similar character to a bill item is valued at that item's rate. A new rate is made only when the work is not similar or the quantity changes beyond the limits in 12.3. More of the same partition is similar work.

Example. The same partition, on another floor, is similar work.
3 / 4

The rate of the Contract carries the mark-ups

In this bill the rates are net and the mark-ups sit below it, so the rate of the Contract is the net rate with the tender mark-ups. Valued at the net rate, a variation loses overheads, risk and profit.

Example. A ceiling variation on the same job (rounded).
60 m2 of ceiling at the net rateUSD2,160.00
Tender mark-upsUSD304.00
Value at the rate of the ContractUSD2,464.00
Common mistake

The net rate

The QS opens the bill, multiplies by the rate on the line and sends it. That rate is net. The valuation must carry the same mark-ups the Client accepted in the tender.

Example. The rate on the bill line is not the whole rate of the Contract here.

Extra ceiling

Same job, suspended ceiling FIN.02, 60 m2 added.

Not to scale
The problem
  • Quantity 60 m2 at net rate USD36.00.
  • Mark-ups 6 %, then 2.5 % and 5 % on the running total.
Step 1 of 2

Net

What is the net amount?

60 × USD36.00 = USD2,160.00.

Step 2 of 2

Value

What is the value at the rate of the Contract?

USD2,160.00 × 1.06 × 1.025 × 1.05 = USD2,464.18.

In short. Similar work: the net bill rate with the tender mark-ups, in the tender's order.

Check yourself

Question 1 of 2

An instruction adds more of a bill item. Which rate applies first?

  • Right.

  • Only for work that is not similar.

  • That is your buying price.

  • Daywork is for work that cannot be measured.

Question 2 of 2

Net amount 4,000; mark-ups 6 %, then 2.5 % and 5 % on the running total. Value?

4,000 × 1.06 × 1.025 × 1.05 = 4,563.23.

Read the source