Rate analysis to CPWD practice (India)

Every rule of the course on one page: how each figure is built, the mistake people usually make, and where it comes up at work. Print it or keep it open while you work.

Task 1

Brickwork: the cheaper source, then the cost per m3

Theory (10 min)
Rule
Compare sources delivered to site. A rate at the source needs carriage for the lead; a delivered rate does not.
How it is built
  • Cost per m³ = W, the cost of the 10 m³ on the sheet ÷ 10
  • W = Bricks delivered to site, cheaper source + Cement and sand + Labour, bhisti included + Scaffolding and sundries
  • Bricks delivered to site = Bricks on the sheet × Cheaper delivered rate: kiln rate plus haul, or the depot's rate
Usual mistake
You used the kiln rate with no haul. Compare delivered prices before you choose the source.
At work
Whenever an item is not in the schedule, the department's estimator analyses its rate like this, and the Executive Engineer checks every line.

Task 2

Two contractor quotes against the CPWD rate

Theory (10 min)
Rule
CPWD analysis: each percentage sits on the total below it, and no GST is added here.
How it is built
  • Complete rate per m³ = W + Water charges, 1 % of W + Profit and overheads, 15 % of W plus water ÷ 10
  • How far quote A is below = Line 2.1 amount at your rate − Quote A's amount for the line
Usual mistake
You added 16 % to W in one go. Water first, then 15 % on W plus water.
At work
When tenders come in, the department compares each quoted rate with its own justified rate before it recommends an award.

Task 3

RCC M25: what belongs in the concrete rate

Theory (11 min)
Rule
One payment per cost. Ask of every sheet line whether the bill pays it somewhere else.
How it is built
  • Complete rate for RCC M25 = W without the TMT bars, plant included + Water charges, 1 % + Profit and overheads, 15 % on W plus water
  • Reinforcement on line 1.3 = 8 mm bars + 10 mm + 12 mm + 16 mm, all from the schedule in kg
  • Overpayment if the bars stay in = Rate with the TMT bars − Your rate × Line 2.2 quantity
Usual mistake
The TMT bars are inside your rate. Reinforcement is paid on line 1.3 by weight; leave it out here.
At work
Auditors look for this first: one cost paid in two bill items. Estimators check every analysis line against the rest of the bill.

Task 4

Schedule items with the cost index, analysed items without

Theory (10 min)
Rule
Non-schedule items are rated on market rates without the cost index. The index is for schedule base rates.
How it is built
  • Estimate total = Section 1 total + Section 2 total
  • Schedule item rate = Base rate × 1.14, the station cost index
Usual mistake
The two analysed items were indexed too. They are at market rates already: no cost index on lines 2.1 and 2.2.
At work
Every CPWD-style estimate mixes schedule items under the station's cost index with analysed non-schedule items, and the sanctioning officer checks both.