Rate analysis to CPWD practice (India)
Every rule of the course on one page: how each figure is built, the mistake people usually make, and where it comes up at work. Print it or keep it open while you work.
- Rule
- Compare sources delivered to site. A rate at the source needs carriage for the lead; a delivered rate does not.
- How it is built
- Cost per m³ = W, the cost of the 10 m³ on the sheet ÷ 10
- W = Bricks delivered to site, cheaper source + Cement and sand + Labour, bhisti included + Scaffolding and sundries
- Bricks delivered to site = Bricks on the sheet × Cheaper delivered rate: kiln rate plus haul, or the depot's rate
- Usual mistake
- You used the kiln rate with no haul. Compare delivered prices before you choose the source.
- At work
- Whenever an item is not in the schedule, the department's estimator analyses its rate like this, and the Executive Engineer checks every line.
- Rule
- CPWD analysis: each percentage sits on the total below it, and no GST is added here.
- How it is built
- Complete rate per m³ = W + Water charges, 1 % of W + Profit and overheads, 15 % of W plus water ÷ 10
- How far quote A is below = Line 2.1 amount at your rate − Quote A's amount for the line
- Usual mistake
- You added 16 % to W in one go. Water first, then 15 % on W plus water.
- At work
- When tenders come in, the department compares each quoted rate with its own justified rate before it recommends an award.
- Rule
- One payment per cost. Ask of every sheet line whether the bill pays it somewhere else.
- How it is built
- Complete rate for RCC M25 = W without the TMT bars, plant included + Water charges, 1 % + Profit and overheads, 15 % on W plus water
- Reinforcement on line 1.3 = 8 mm bars + 10 mm + 12 mm + 16 mm, all from the schedule in kg
- Overpayment if the bars stay in = Rate with the TMT bars − Your rate × Line 2.2 quantity
- Usual mistake
- The TMT bars are inside your rate. Reinforcement is paid on line 1.3 by weight; leave it out here.
- At work
- Auditors look for this first: one cost paid in two bill items. Estimators check every analysis line against the rest of the bill.
- Rule
- Non-schedule items are rated on market rates without the cost index. The index is for schedule base rates.
- How it is built
- Estimate total = Section 1 total + Section 2 total
- Schedule item rate = Base rate × 1.14, the station cost index
- Usual mistake
- The two analysed items were indexed too. They are at market rates already: no cost index on lines 2.1 and 2.2.
- At work
- Every CPWD-style estimate mixes schedule items under the station's cost index with analysed non-schedule items, and the sanctioning officer checks both.