Cheat sheet

Elemental cost planning at concept stage (UK, RICS NRM 1)

Every rule of the course on one page: how each figure is built, the mistake people usually make, and where it comes up at work. Print it or keep it open while you work.

Task 1

GIFA and the order-of-cost estimate

Theory (9 min)
Rule
GIFA is measured inside the external walls. The benchmark moves to the base date first, then to the location.
How it is built
  • Gross internal floor area = Ground floor, inside the external walls + First and second floors, less the atrium void + Enclosed plant room
  • Adjusted rate, £ per m² GIFA = Benchmark rate × Index at the base date ÷ index at the benchmark date × Location factor
  • Order-of-cost estimate = Gross internal floor area × Adjusted rate
Usual mistake
The walls are still in. Take the 0.40 m thickness off both ends of each dimension to reach the inside faces.
At work
At RIBA Stage 2 every cost consultant does this within days of the first drawings, and the client's budget is set from it.

Task 2

The elemental cost plan

Theory (9 min)
Rule
Each element has its own measure. Substructure takes the lowest floor, upper floors the floors above it.
How it is built
  • Elemental estimate per m² GIFA = Direct cost of elements 1 to 8 ÷ Gross internal floor area
  • Against the order of cost, % = (Direct cost − order-of-cost estimate) ÷ Order-of-cost estimate × 100
Usual mistake
Substructure is priced on the lowest floor only: its unit rate already covers the foundations of the whole building.
At work
Every cost plan you issue is elemental, and the client's project manager reads it group by group against the brief.

Task 3

From building works to the cost limit

Theory (10 min)
Rule
Preliminaries, then overheads and profit, then risk, then inflation. The two risks share one base; inflation compounds.
How it is built
  • Tender price inflation, % = (1 + 1Q2027 rate) × (1 + 2Q2027 rate) × (1 + 3Q2027 rate) − 1 × 100
  • Cost limit including inflation = Building works + Preliminaries + Overheads and profit + Design development risk + Construction risk + Tender price inflation
Usual mistake
Prices compound: multiply (1 + each rate) and take 1 away at the end.
At work
Every NRM 1 cost plan carries these rows, and the client's auditor checks the base of each one.

Task 4

Value engineering: steel frame and rendered walls

Theory (9 min)
Rule
An option replaces, reduces and adds. The percentage rows carry the saving through to the cost limit; the redesign fee comes off last.
How it is built
  • Saving at the cost limit = Cost limit, cost plan 1 − New grand total, option B
  • Saving after the redesign cost = Saving at the cost limit − Redesign fee
Usual mistake
The percentage rows act on the saving too. Read the new grand total and take it from cost plan 1.
At work
When a design is over budget, the QS prices options like this for the design team meeting, and the client chooses from them.

Task 5

Reconcile cost plan 2 to the budget

Theory (8 min)
Rule
Compare like with like. Divide VAT out, take off fees and other costs, then subtract the plan.
How it is built
  • Construction budget = Budget letter total ÷ 1.20, VAT out − Fees and other project costs
  • Variance to the construction budget = Construction budget − Grand total, cost plan 2
  • Cost check, £ per m² GIFA = Grand total, cost plan 2 ÷ Gross internal floor area
Usual mistake
VAT is inside the price: divide by 1.20 to take it out. Taking 20 % off removes too much.
At work
Every cost report ends with this reconciliation, and the client's finance team decides from it whether the scheme can proceed.