Cheat sheet
Elemental cost planning at concept stage (UK, RICS NRM 1)
Every rule of the course on one page: how each figure is built, the mistake people usually make, and where it comes up at work. Print it or keep it open while you work.
- Rule
- GIFA is measured inside the external walls. The benchmark moves to the base date first, then to the location.
- How it is built
- Gross internal floor area = Ground floor, inside the external walls + First and second floors, less the atrium void + Enclosed plant room
- Adjusted rate, £ per m² GIFA = Benchmark rate × Index at the base date ÷ index at the benchmark date × Location factor
- Order-of-cost estimate = Gross internal floor area × Adjusted rate
- Usual mistake
- The walls are still in. Take the 0.40 m thickness off both ends of each dimension to reach the inside faces.
- At work
- At RIBA Stage 2 every cost consultant does this within days of the first drawings, and the client's budget is set from it.
- Rule
- Each element has its own measure. Substructure takes the lowest floor, upper floors the floors above it.
- How it is built
- Elemental estimate per m² GIFA = Direct cost of elements 1 to 8 ÷ Gross internal floor area
- Against the order of cost, % = (Direct cost − order-of-cost estimate) ÷ Order-of-cost estimate × 100
- Usual mistake
- Substructure is priced on the lowest floor only: its unit rate already covers the foundations of the whole building.
- At work
- Every cost plan you issue is elemental, and the client's project manager reads it group by group against the brief.
- Rule
- Preliminaries, then overheads and profit, then risk, then inflation. The two risks share one base; inflation compounds.
- How it is built
- Tender price inflation, % = (1 + 1Q2027 rate) × (1 + 2Q2027 rate) × (1 + 3Q2027 rate) − 1 × 100
- Cost limit including inflation = Building works + Preliminaries + Overheads and profit + Design development risk + Construction risk + Tender price inflation
- Usual mistake
- Prices compound: multiply (1 + each rate) and take 1 away at the end.
- At work
- Every NRM 1 cost plan carries these rows, and the client's auditor checks the base of each one.
- Rule
- An option replaces, reduces and adds. The percentage rows carry the saving through to the cost limit; the redesign fee comes off last.
- How it is built
- Saving at the cost limit = Cost limit, cost plan 1 − New grand total, option B
- Saving after the redesign cost = Saving at the cost limit − Redesign fee
- Usual mistake
- The percentage rows act on the saving too. Read the new grand total and take it from cost plan 1.
- At work
- When a design is over budget, the QS prices options like this for the design team meeting, and the client chooses from them.
- Rule
- Compare like with like. Divide VAT out, take off fees and other costs, then subtract the plan.
- How it is built
- Construction budget = Budget letter total ÷ 1.20, VAT out − Fees and other project costs
- Variance to the construction budget = Construction budget − Grand total, cost plan 2
- Cost check, £ per m² GIFA = Grand total, cost plan 2 ÷ Gross internal floor area
- Usual mistake
- VAT is inside the price: divide by 1.20 to take it out. Taking 20 % off removes too much.
- At work
- Every cost report ends with this reconciliation, and the client's finance team decides from it whether the scheme can proceed.