Estimating under ÖNORM B 2061: K3, K7 and a claim for extra costs

Every rule of the course on one page: how each figure is built, the mistake people usually make, and where it comes up at work. Print it or keep it open while you work.

Task 1

K3: the crew's hourly rate

Theory (11 min)
Rule
Cost into the bill, price into K7. B18 for the cost estimate, B21 = B18 + overall markup for the price.
How it is built
  • Personnel cost B15 = Crew wage B10 + Direct and apportioned payroll on-costs + Daily allowance B11
  • Average wage cost B18 = B15 + Personnel overheads B16
  • Unit rate 02.03 = Labour constant × Hourly rate B18
Usual mistake
B21 already holds the overall markup. The bill is at cost and K2 comes as markup rows: enter B18.
At work
Before every bid, the estimating department recalculates the K3 sheet with the current collective agreement.

Task 2

K7 and K2: markups on the right base

Theory (11 min)
Rule
Labour at B21, other costs × 1,1781. The bill holds cost; K2 sits on it as four rows.
How it is built
  • Unit rate 03.01 per K7 = Labour constant × average wage price + Other costs × (1 + overall markup)
  • Shortfall of the simple sum = Grand total in the ERP − Direct cost × (1 + simple sum of the markups)
Usual mistake
The overall markup is 17,81 %, not the plain sum of 17 %.
At work
In every bid, the estimating department sets the overall markup from the K2 sheet and checks it against the grand total.

Task 3

Claim for extra costs under ÖNORM B 2110

Theory (11 min)
Rule
New rate from the old basis. Labour constant of the comparable item, material at the bid's price basis.
How it is built
  • New unit rate = Labour constant of 03.02 × average wage price + Other costs at the bid's price basis × (1 + overall markup)
  • Claim for extra costs = Quantity × (new rate − rate of 03.01)
Usual mistake
The 165,00 m² of inner wall drop out: extra = quantity × (new rate − rate of 03.01).
At work
When the client's site supervision (ÖBA) orders a change, the site manager notifies the extra costs and prices them from the original estimate.

Task 4

Interim invoice with cover retention

Theory (9 min)
Rule
20 % VAT, 5 % cover retention on the net. The town is no construction business: no reverse charge.
How it is built
  • Amount payable = Work done, net + VAT − Cover retention
Usual mistake
The town is no construction business: section 19(1a) does not apply, the invoice carries 20 % VAT.
At work
Every month the site manager raises an interim invoice from the measured progress, with VAT and cover retention.

Task 5

Final invoice and defects retention

Theory (10 min)
Rule
The defects retention replaces the cover retention. 2 % of the final invoice; deduct what was actually paid.
How it is built
  • Final invoice, net = Contract sum + Accepted extra costs
  • Defects retention = Final invoice, net × Rate of the defects retention
  • Balance due = Final invoice net + VAT − Amount paid on the first interim invoice − Defects retention
Usual mistake
The cover retention is replaced by the defects retention: do not deduct it again.
At work
After handover, the site manager raises the final invoice with all accepted claims and the defects retention.