Cheat sheet
Estimating under ÖNORM B 2061: K3, K7 and a claim for extra costs
Every rule of the course on one page: how each figure is built, the mistake people usually make, and where it comes up at work. Print it or keep it open while you work.
- Rule
- Cost into the bill, price into K7. B18 for the cost estimate, B21 = B18 + overall markup for the price.
- How it is built
- Personnel cost B15 = Crew wage B10 + Direct and apportioned payroll on-costs + Daily allowance B11
- Average wage cost B18 = B15 + Personnel overheads B16
- Unit rate 02.03 = Labour constant × Hourly rate B18
- Usual mistake
- B21 already holds the overall markup. The bill is at cost and K2 comes as markup rows: enter B18.
- At work
- Before every bid, the estimating department recalculates the K3 sheet with the current collective agreement.
- Rule
- Labour at B21, other costs × 1,1781. The bill holds cost; K2 sits on it as four rows.
- How it is built
- Unit rate 03.01 per K7 = Labour constant × average wage price + Other costs × (1 + overall markup)
- Shortfall of the simple sum = Grand total in the ERP − Direct cost × (1 + simple sum of the markups)
- Usual mistake
- The overall markup is 17,81 %, not the plain sum of 17 %.
- At work
- In every bid, the estimating department sets the overall markup from the K2 sheet and checks it against the grand total.
- Rule
- New rate from the old basis. Labour constant of the comparable item, material at the bid's price basis.
- How it is built
- New unit rate = Labour constant of 03.02 × average wage price + Other costs at the bid's price basis × (1 + overall markup)
- Claim for extra costs = Quantity × (new rate − rate of 03.01)
- Usual mistake
- The 165,00 m² of inner wall drop out: extra = quantity × (new rate − rate of 03.01).
- At work
- When the client's site supervision (ÖBA) orders a change, the site manager notifies the extra costs and prices them from the original estimate.
- Rule
- 20 % VAT, 5 % cover retention on the net. The town is no construction business: no reverse charge.
- How it is built
- Amount payable = Work done, net + VAT − Cover retention
- Usual mistake
- The town is no construction business: section 19(1a) does not apply, the invoice carries 20 % VAT.
- At work
- Every month the site manager raises an interim invoice from the measured progress, with VAT and cover retention.
- Rule
- The defects retention replaces the cover retention. 2 % of the final invoice; deduct what was actually paid.
- How it is built
- Final invoice, net = Contract sum + Accepted extra costs
- Defects retention = Final invoice, net × Rate of the defects retention
- Balance due = Final invoice net + VAT − Amount paid on the first interim invoice − Defects retention
- Usual mistake
- The cover retention is replaced by the defects retention: do not deduct it again.
- At work
- After handover, the site manager raises the final invoice with all accepted claims and the defects retention.