Cheat sheet
Claims and extension of time (Saudi Arabia, FIDIC)
Every rule of the course on one page: how each figure is built, the mistake people usually make, and where it comes up at work. Print it or keep it open while you work.
- Rule
- The 28 days run from awareness: the day the site knew, or should have known, of the delay.
- How it is built
- Awareness date = First diary day the delay showed on site + Event logged that day
- Days to the notice = Calendar days left in May after awareness + Days of June up to the notice
- Usual mistake
- An RFI is a question, not a delay. Count from the first day the late drawings held up the work.
- At work
- Claims managers keep the site diary for exactly this: it proves the day the trouble began.
- Rule
- A late Notice stands if the Engineer stays silent for 14 days after receiving it (Sub-Clause 20.2.2).
- How it is built
- Days late = Days from the rock to the notice − the 28 days allowed
- The Engineer's days = Days from receipt of NOC-01 to the Engineer's letter
- Usual mistake
- Subtract the 28 days allowed by Sub-Clause 20.2.1. Late means the days after 04/04/2027.
- At work
- Every claims register tracks two clocks for each notice: the Contractor's and the Engineer's.
- Rule
- Only a delay on the critical path moves Completion. Float absorbs the rest.
- How it is built
- Critical path = Longest chain of linked activities
- Float of A060 = Programme length − A060's own duration
- Extension of time = Delay to the critical activity, counted to the day work restarted
- Usual mistake
- The rock delay sits in A060's float. The roof slab delay is the one on the critical path.
- At work
- Every extension of time claim starts from the programme: planners show which chain of work sets the finish date.
- Rule
- Cost from the records, profit only where the clause gives it, and no VAT in the claim.
- How it is built
- Cost = Site overheads per day × delay days + Idle crew cost + Formwork hire × delay days
- Cost Plus Profit = Cost × (1 + profit percentage)
- Usual mistake
- Sub-Clause 1.9 gives Cost Plus Profit. Add 5 % on the Cost.
- At work
- Quantity surveyors price delay claims from the cost ledger, and the Engineer checks each line against it.
- Rule
- 84 days from awareness, the same start as the 28: the Notice does not restart the clock.
- How it is built
- Last day for the detailed claim = Awareness date + 84 days
- Days left = Last day − Today's date
- Usual mistake
- The 84 days run from awareness on 16/05/2027, not from the Notice.
- At work
- Claims managers diary both deadlines the day a delay starts, so the detailed claim is never filed late.