Cheat sheet

Claims and extension of time (Saudi Arabia, FIDIC)

Every rule of the course on one page: how each figure is built, the mistake people usually make, and where it comes up at work. Print it or keep it open while you work.

Task 1

When did the clock start? Awareness and the 28 days

Theory (9 min)
Rule
The 28 days run from awareness: the day the site knew, or should have known, of the delay.
How it is built
  • Awareness date = First diary day the delay showed on site + Event logged that day
  • Days to the notice = Calendar days left in May after awareness + Days of June up to the notice
Usual mistake
An RFI is a question, not a delay. Count from the first day the late drawings held up the work.
At work
Claims managers keep the site diary for exactly this: it proves the day the trouble began.

Task 2

Notices of Claim and the late Notice

Theory (9 min)
Rule
A late Notice stands if the Engineer stays silent for 14 days after receiving it (Sub-Clause 20.2.2).
How it is built
  • Days late = Days from the rock to the notice − the 28 days allowed
  • The Engineer's days = Days from receipt of NOC-01 to the Engineer's letter
Usual mistake
Subtract the 28 days allowed by Sub-Clause 20.2.1. Late means the days after 04/04/2027.
At work
Every claims register tracks two clocks for each notice: the Contractor's and the Engineer's.

Task 3

Which delay moves Completion? The critical path

Theory (11 min)
Rule
Only a delay on the critical path moves Completion. Float absorbs the rest.
How it is built
  • Critical path = Longest chain of linked activities
  • Float of A060 = Programme length − A060's own duration
  • Extension of time = Delay to the critical activity, counted to the day work restarted
Usual mistake
The rock delay sits in A060's float. The roof slab delay is the one on the critical path.
At work
Every extension of time claim starts from the programme: planners show which chain of work sets the finish date.

Task 4

Cost Plus Profit for the late drawings

Theory (10 min)
Rule
Cost from the records, profit only where the clause gives it, and no VAT in the claim.
How it is built
  • Cost = Site overheads per day × delay days + Idle crew cost + Formwork hire × delay days
  • Cost Plus Profit = Cost × (1 + profit percentage)
Usual mistake
Sub-Clause 1.9 gives Cost Plus Profit. Add 5 % on the Cost.
At work
Quantity surveyors price delay claims from the cost ledger, and the Engineer checks each line against it.

Task 5

The fully detailed Claim: 84 days

Theory (9 min)
Rule
84 days from awareness, the same start as the 28: the Notice does not restart the clock.
How it is built
  • Last day for the detailed claim = Awareness date + 84 days
  • Days left = Last day − Today's date
Usual mistake
The 84 days run from awareness on 16/05/2027, not from the Notice.
At work
Claims managers diary both deadlines the day a delay starts, so the detailed claim is never filed late.