Cheat sheet

CPM schedule and time extensions (US, AIA A201)

Every rule of the course on one page: how each figure is built, the mistake people usually make, and where it comes up at work. Print it or keep it open while you work.

Task 1

Durations and logic of the remaining work

Theory (10 min)
Rule
Round up to a whole working day. Crews add output; a week is five working days.
How it is built
  • Q010 duration = Drywall area ÷ (Daily output per crew × crews) Rounded up to whole days
  • Q030 duration = Paint area, both levels ÷ (Daily output per painter × painters) Rounded up to whole days
Usual mistake
That is one crew. Two crews work each level: divide by their combined output.
At work
At each monthly update, the scheduler recalculates the remaining durations from quantities left and the crews on site.

Task 2

Critical path, float and the planned finish

Theory (11 min)
Rule
The longest path sets the finish, not the longest bar. Float is counted in working days.
How it is built
  • Planned length = Largest early finish of all activities
  • Q090 total float = Late start of Q090 − Early start of Q090
Usual mistake
The longest bar is not always critical. Compare its path with the fit-out path.
At work
After every update, the scheduler runs the critical path and reports the float to the project team.

Task 3

An owner change off the critical path

Theory (10 min)
Rule
Time follows the finish, not the activity. A change with float behind it moves nothing.
How it is built
  • Q060 total float after CO-05 = Float before the change − Days added by CO-05
  • Extension of Contract Time = New finish date − Old finish date
Usual mistake
Those are the days added to Q060. Q060 had float: the finish did not move.
At work
For each change order, the scheduler adds its days to the schedule and checks whether the finish date moves.

Task 4

An owner change on the critical path: the fragnet

Theory (12 min)
Rule
State the extension in calendar days. A201 counts a day as a calendar day.
How it is built
  • Q040 after CO-03 = Q040 duration − Days of the deleted laminate tops
  • Planned length after CO-03 = Path through Q040, Q045 and Q050
  • Extension in calendar days = New finish date − Previous finish date
Usual mistake
The fragnet runs beside the trim-out. The sinks need the tops: Q045 goes before Q050.
At work
When a change hits critical work, the scheduler inserts a fragnet and submits it with the request for more time.

Task 5

Abnormal weather and a concurrent delay

Theory (12 min)
Rule
Only abnormal weather earns time, measured alone on the current update. Your own delay earns none.
How it is built
  • Abnormal weather days = Days lost − Normal weather days already planned
  • Weather delay to the finish = New length with the weather − Length before the weather
Usual mistake
That is the whole slip, the electrician included. Measure the weather alone.
At work
After bad weather, the scheduler compares days lost with the normal days planned and claims only the abnormal days that moved the finish.