Cheat sheet
CPM schedule and time extensions (US, AIA A201)
Every rule of the course on one page: how each figure is built, the mistake people usually make, and where it comes up at work. Print it or keep it open while you work.
- Rule
- Round up to a whole working day. Crews add output; a week is five working days.
- How it is built
- Q010 duration = Drywall area ÷ (Daily output per crew × crews) Rounded up to whole days
- Q030 duration = Paint area, both levels ÷ (Daily output per painter × painters) Rounded up to whole days
- Usual mistake
- That is one crew. Two crews work each level: divide by their combined output.
- At work
- At each monthly update, the scheduler recalculates the remaining durations from quantities left and the crews on site.
- Rule
- The longest path sets the finish, not the longest bar. Float is counted in working days.
- How it is built
- Planned length = Largest early finish of all activities
- Q090 total float = Late start of Q090 − Early start of Q090
- Usual mistake
- The longest bar is not always critical. Compare its path with the fit-out path.
- At work
- After every update, the scheduler runs the critical path and reports the float to the project team.
- Rule
- Time follows the finish, not the activity. A change with float behind it moves nothing.
- How it is built
- Q060 total float after CO-05 = Float before the change − Days added by CO-05
- Extension of Contract Time = New finish date − Old finish date
- Usual mistake
- Those are the days added to Q060. Q060 had float: the finish did not move.
- At work
- For each change order, the scheduler adds its days to the schedule and checks whether the finish date moves.
- Rule
- State the extension in calendar days. A201 counts a day as a calendar day.
- How it is built
- Q040 after CO-03 = Q040 duration − Days of the deleted laminate tops
- Planned length after CO-03 = Path through Q040, Q045 and Q050
- Extension in calendar days = New finish date − Previous finish date
- Usual mistake
- The fragnet runs beside the trim-out. The sinks need the tops: Q045 goes before Q050.
- At work
- When a change hits critical work, the scheduler inserts a fragnet and submits it with the request for more time.
- Rule
- Only abnormal weather earns time, measured alone on the current update. Your own delay earns none.
- How it is built
- Abnormal weather days = Days lost − Normal weather days already planned
- Weather delay to the finish = New length with the weather − Length before the weather
- Usual mistake
- That is the whole slip, the electrician included. Measure the weather alone.
- At work
- After bad weather, the scheduler compares days lost with the normal days planned and claims only the abnormal days that moved the finish.